SJC Home
Clearance Sheet C2021-003540*003

 Department IssuesSigned OffIntl

Plan reviewed for new, automatic wet fire sprinkler system. 6” fire main to a 2.5” sprinkler riser.

Reviewed using FFPC 7th edition effective Dec. 31, 2020. NFPA 1 and 101 references are Florida Editions of the code in the FFPC.

Reviewer: D. Feagle 904-209-1721, dfeagle@sjcfl.us

4/13/2022, Resubmission Reviewer: Aaron Connell 904-599-8253, aconnell@sjcfl.us

To schedule fire inspections please call 827-6842 (automated system). Questions about inspections please call 209-1740x1.
Review by the AHJ shall not relieve the applicant of the responsibility for compliance with the Code.
4/13/2022 aConnell

RESUBMITTING:
A. Make necessary changes and resubmit everything in person to the Permit Center.
B. Once at the Permit Center swap out altered pages in EACH plan set (job and office). One copy of the removed/old pages will need to be resubmitted and labeled "OLD". Do not forget to remove pages for work not associated in this permit.
C. Provide a response to comments along with any supporting documentation.  Response to comments is REQUIRED not optional.
- The response to comments sheet will need to include a response to each numbered comment and tell us where in the plans the comment was addressed. Ex - "top left of page A11" or "Page E1 note 8".
- Code responses shall reference Florida Fire Prevention Code 7th Ed. (not Building Code)

4/13/2022, A Connell: Responses to all comments have been submitted with the resubmittal.

4/13/2022 aConnell

NOTE: Florida Administrative Code (FAC) 61G15-32.003 defines a material deviation as "Any deviation from the design parameters established and documented by the Engineer of Record." Furthermore FAC 61G15-32.003(6) states "When layout documents contain material deviation from the Engineer of Record's Fire Protection System Engineering Document, such layout documents are not compliant unless they are accompanied by revised Engineering Documents made and sealed by the Engineer of record for the Fire Protection System."

Approved Construction Plans (permit 12114021), Sheet FP0.1 provides 61G15-32 data. The submitted shop drawings are not sealed and are subject to the 61G15-32 data.

4/13/2022 aConnell

1) The shop drawings indicate the design approach for the Light Hazard areas to be .10/900 SF. Construction plans Sheet FP0.1 61G153-32.004 2(d) requires .10/1500 SF.

a) Adjust the Shop Drawings to match the 61G15-32.004 2(d) OR,

b) Have the Engineer of Record adjust the 61G15-32.004 2(d) to match the Shop Drawings.

4/13/2022, A Connell: The shop drawings for the design approach for Light Hazard areas have been adjusted to reflect; .10/1500 SF.

4/13/2022 aConnell

2) I was not able to locate the remote/most demanding area for Ordinary Hazard Group 1 used on the plans.

Show on plans the Ordinary Hazard Group 1 remote area.

4/13/2022, A Connell: The Ordinary Hazard areas that were identified are the Storage Room and the Janitors Room, and they have been identified on the shop drawings.

4/13/2022 aConnell

3) The riser detail does not provide enough detail as drawn to make out the equipment layout.

Provide a more detailed drawing.

4/13/2022, A Connell: All riser equipment has been identified on the riser detail.

4/13/2022 aConnell

4) Construction Plans Sheet FP0.1 indicates a supervised double check backflow preventer (watts 757 or equal) located on the sprinkler riser with two tamper switch shutoff valves (before and after the double check valve).

a) Adjust the shop drawings to match the engineer of records riser requirements OR,

b) Have the EOR revise Sheet FP0.1 to match the shop drawings

4/13/2022, A Connell: Noted FP0.1 Riser Requirments appear to have been updated to reflect shop drawings and back-flow preventer has is not shown on the riser detail. Back-flow is to be on the site fire plan.

4/13/2022 aConnell

5) Missing the pressure gauge above the system check valve located below the FDC connection. 13:7.1.1.2

Provide the missing pressure gauge.

4/13/2022, A Connell: Shop Plans and Riser Detail both indicate Above and Below pressure gauges on the check valve with coordinating specifications.

4/13/2022 aConnell

6) Riser detail did not identify a pressure relief valve or an auxiliary air reservoir. 13:7.1.2.1, 13:7.1.2.2

Provide either a relief valve or an auxiliary reservoir.

4/13/2022, A Connell: Pressure relief valve is now identified on the shop plans and riser detail.

4/13/2022 aConnell

7) No spare sprinkler head box shown on plans. 13:6.2.9

4/13/2022, A Connell: Spare sprinkler-head box is now identified on plans.

4/13/2022 aConnell

8) All above ground fire main and sprinkler control valves are to be provided with tamper switches and monitored in accordance with 101:9.7.2. 101:16.3.6(2) & (5)(a)

4/13/2022, A Connell: Response: Sprinkler control valve shall have tamper switches and shall be monitored. (Note below riser)

4/13/2022 aConnell

9) Please be advised, It has come to my attention at the time of this review that the underground fire main and the Fire Sprinkler Main into the building will be upsized. Please verify the new pipe size and the sprinkler calculations for this system based on the new supply main sizes.

The resubmitted plans need to reflect the correct supply sizes. Once the underground revision has been approved, should the above-ground plans not match the revised underground plans, the above ground plans will be required to be revised.

4/13/2022, A Connell: Noted all riser and supply to this location is shown to be 6" main and calculations reflect a 6" Main.

4/13/2022 aConnell