SJC Home
Clearance Sheet C2020-007158

 Department IssuesSigned OffIntl

Plans for a 6" DR 18 underground fire main, that will supply the fire sprinkler system and 2 private fire hydrants.  The main will terminate 1'AFF using an in building riser.  The FDC is remote and will be tied into the riser. 


                                                        
Reviewed using FFPC 7th edition effective Dec. 31, 2020.
Reviewer: PJ Webb 904 209 1744 pwebb@sjcfl.us
 
To schedule fire inspections please call 827-6842 (automated system). Questions about inspections please call 209-1740x1.
Review by the AHJ shall not relieve the applicant of the responsibility for compliance with the Code.
 
For questions regarding comments you may reach me at either: 904 209 1744 or pwebb@sjcfl.us.

7/27/2023 PWebb

RESUBMITTING:
A. Make necessary changes and resubmit everything in person to the permit center.
B. Once at the Permit Center swap out altered pages or insert new pages in EACH plan set (Job and Office). One copy of the removed/old pages from the JOB Copy will need to be submitted and marked "OLD". Do not forget to remove pages for work not associated to this permit. All plan papers must be the same size.
C. Provide a response to comments along with any supporting documentation. Response to comments is REQUIRED not optional.
- The response to comments sheet will need to include a response to each numbered comment and tell us where in the plans the comments was addressed. EX - "Top Left of Page E1-1" or "Page E1 Note 8".
- Code responses shall reference Florida Fire Prevention Code 7th Ed.

7/27/2023 PWebb

1) Remove the note indicating approval of plans do not include approval for private underground water main.....

This review is for the approval of the underground. 

------------

Thursday, July 27, 2023 PJ- Note has been removed. 

7/27/2023 PWebb

2) FDC connection on piping up to 2 inches shall be equipped with a Double Clapper Siamese Connection.

FDC connections on piping LARGER than 2 inches shall be equipped with a five (5) inch Storz connection and shall have a 30 degree downward deflection.

This applies to all FDC’s regardless being on a building or free standing.

This includes Standpipe FDC's. 

NFPA 24:5.9.1.2, and 5.9.2.4

----------------

Thursday, July 27, 2023 PJW- Note added to plans indicating Storz.

7/27/2023 PWebb

3) Provide a FDC detail.  Ensure that it is Storz, and that it shows the check valve and drain.  NFPA 24:5.9.3.1, 5.9.4.1. 

---------------

Thursday, July 27, 2023 PJW- No details provided.  Ensure that the check valve and drain valve is installed per the above sections.  This will be verified at final.   

 

7/27/2023 PWebb

4) The main shown in the plans stops short of the building.  Per FSS 633.334(3) the underground is to terminate 1' above finished floor.  Show continuation to building and note 1'AFF termination. 

--------------

Thursday, July 27, 2023 PJW- Main extended, note added. 

7/27/2023 PWebb

5) The specs provided for the FDC are for a Siamese.  Provide the storz specifications. 

-------------------------------

Thursday, July 27, 2023- Note added to plans indicating Storz. 

7/27/2023 PWebb

6) Provide a hydrant detail.  Ensure that the slab under the hydrant is shown per NFPA 24:7.3.1.  The annex has an image of this requirement.   Just FYI the county and JEA standard details do not show this requirement.

------------------------

Thursday, July 27, 2023 PJW- Hydrant detail sheet C-12.   

7/27/2023 PWebb

7) What size main is the FDC main? 

-----------------

Thursday, July 27, 2023 PJW- Plans updated to indicate 4"

7/27/2023 PWebb

8) Identify the bury depth on the plans.  NFPA 24:4.1.3(8)(8h), 24:10.4.2. 

-----------------

Thursday, July 27, 2023 PJW- Note 15 added to sheet C3.1 indicating 4' bury depth. 

7/27/2023 PWebb

9) Show the hydrant valve on the plans.  Ensure that it is no more than 20 feet from the hydrant.  NFPA 24:7.1.1.2, 7.1.1.2.1.

-----------------

Thursday, July 27, 2023 PJW- Hydrant Valves indicated on the plans within the 20'.

7/27/2023 PWebb

10) The hydrant at the rear of the building is closer than 40 feet to the building (approx. 20').  Hydrant cannot be within 40 of the building per 24:7.2.3. 

---------------

Thursday, July 27, 2023 PJW- Hydrant relocated to other side of the parking area.

7/27/2023 PWebb

11) Show the pipe lengths on the plans for each segment.  NFPA 24:4.1.3(8)(8b)

-------------

Thursday, July 27, 2023 PJW- Pipe lengths indicated on the plans. 

7/27/2023 PWebb