Clearance Sheet C2020-005248

 Department IssuesSigned OffIntl

Plan reviewed for a 336 SF addition including a walk-in cooler/freezer and expanding the size of the existing office. Construction type is VB , non-sprinkled.


Reviewed using FFPC 6th edition effective Dec. 31, 2017. NFPA 1 and 101 references are Florida Editions of the code in the FFPC.

Plans are APPROVED.

Reviewer: D. Feagle 904-209-1721

To schedule fire inspections please call 827-6842 (automated system). Questions about inspections please call 209-1740x1.
Review by the AHJ shall not relieve the applicant of the responsibility for compliance with the Code.  

10/8/2020 dfeagle

Door schedule on page A1.1 under the hardware-set column doors 100 and 101 have "N/A" identified.

Thursday, October 8, 2020 1355 hrs. Spoke with Contractor Les Gallagher regarding doors 100 and 101 locking arrangements. Mr. Gallagher said that he will be putting latching hardware on the doors. I explained the action the door latching hardware is required to operate.

The releasing mechanism of the door latch shall open the door leaf with no more than one (1) releasing operation. NFPA 101:7.2.1.5.10.2

In other words, when the door is locked you should only have to from the egress side of the door grab the handle, turn the handle and push/pull the door to open it. If you have to unlock the door first the latching mechanism is not correct.

The fire inspector will at fire final verify this requirement. Be prepared to show the door hardware specification sheets at the fire final.

10/8/2020 dfeagle