SJC Home
Clearance Sheet C2019-005506*007

 Department IssuesSigned OffIntl

Plan for a 1000sf interior buildout for a café that opens into the core building area, that does not have any indication of grease producing cooking equipment.  There is an oven indicated.  If cooking is performed or any equipment is used to cook that produces grease laden vapers, commercial ventilation and fire suppression will be required.  This included the use of any tabletop cooking equipment. (hot plates, sandwich presses etc. )  The plan is APPROVED as submitted. 

Note: This plan was also submitted as mixed assembly and business.  It was reviewed as solely business since I did not see an assembly component.  PJW Thursday, March 26, 2020


                                                        
Reviewed using FFPC 6th edition effective Dec. 31, 2017.
Reviewer: PJ Webb 904 209 1744
 
To schedule fire inspections please call 827-6842 (automated system). Questions about inspections please call 209-1740x1.
Review by the AHJ shall not relieve the applicant of the responsibility for compliance with the Code.

3/26/2020 PWebb

INFORMATIONAL ONLY NO RESPONSE NECESSARY:
The system(s) outlined in this set of plans is conceptual.

A HOLD has been placed at framing (105) until either: a) a permit has been pulled or b) a letter submitted from respective system contractor indicating no work to be done to the existing system:
- fire alarm system
- fire sprinkler system

3/26/2020 PWebb