Plans for a 1500 sf interior remodel within an existing building that does have fire sprinklers and a fire alarm system.  The space is indicated on the plans as mixed assembly and business.  The plan was reviewed as business.  Plans NOT APPROVED for the following reasons. 

Note: Attempted to contact architect and engineer, got general mailbox.   

-----------

Plans APPROVED. PJW Friday, April 24, 2020


                                                        
Reviewed using FFPC 6th edition effective Dec. 31, 2017.
Reviewer: PJ Webb 904 209 1744
 
To schedule fire inspections please call 827-6842 (automated system). Questions about inspections please call 209-1740x1.
Review by the AHJ shall not relieve the applicant of the responsibility for compliance with the Code.

4/24/2020 PWebb

The plan summary indicates that the space is designed as mixed assembly and business.  Please take a second look at the classification.  Unless I am missing something, I do not see an assembly component.  If it is truly an assembly, the space would require 2 means of egress.   Modify the plans accordingly. 

--------------

Assembly has been removed from the code summary.  Space is business. PJW Friday, April 24, 2020 

4/24/2020 PWebb

Ensure that doors 1206 (x2) and 1204 are provided with closers and latches since they are in a smoke partition.  NFPA 101:8.4.3.5 and 8.5.4.4. and 8.5.4.3.

-----------------

Acknowledged on RTC.  PJW Friday, April 24, 2020 

4/24/2020 PWebb

At the time of fire final be prepared to provide a copy of the manufacturer specification sheets to the fire inspector showing that each interior finish will meet:

- wall and ceiling finish will meet Class A, B or C. 101:38.3.3.2.2

- floor finish shall meet either: a) ASTM D 2859 for carpet and carpet like materials or b) has a minimum critical radiant flux of .1 W/cm2 for non carpet flooring. 101:38.3.3.3.3.

If there are multiple finishes, label each spec sheet identifying each product, its location AND highlight the area showing illustrating it meets the applicable Code requirement.

4/24/2020 PWebb

There are two HVAC ducts that penetrate the smoke barrier as indicated on sheet M2.1dd.  I do not see an indication of proposed smoke dampers.  Please identify on the plans.  Ensure that the dampers are rated for at least class 2 smoke leakage and have an elevated temperature rating of at least 250 degrees.  NFPA 101:8.4.6.2 and 8.4.6.3. 

-------------

Dampers indicated on the plans.  Damper inspection hold added to the permit.  PJW Friday, April 24, 2020

4/24/2020 PWebb

INFORMATIONAL ONLY NO RESPONSE NECESSARY:
The system(s) outlined in this set of plans is conceptual.

A HOLD has been placed at framing (105) until either: a) a permit has been pulled or b) a letter submitted from respective system contractor indicating no work to be done to the existing system:
- fire alarm system
- fire sprinkler system
- Smoke dampers

4/24/2020 PWebb