SJC Home
Clearance Sheet C2019-005506*003

 Department IssuesSigned OffIntl

Plans for a 3100 square foot interior buildout of an existing 2 story office building that has an existing fire alarm and sprinkler system in place.  The plans were submitted and reviewed as Business.  The plans are NOT APPROVED for the following reasons.   


                                                        
Reviewed using FFPC 6th edition effective Dec. 31, 2017.
Reviewer: PJ Webb 904 209 1744
 
To schedule fire inspections please call 827-6842 (automated system). Questions about inspections please call 209-1740x1.
Review by the AHJ shall not relieve the applicant of the responsibility for compliance with the Code.

 

The occupant load factor utilized for the therapy gym is 50.  Provide FFE (fixture, furniture and equipment) plans for the gym area showing the layout of the proposed gym equipment.  If no equipment will be used then the factor used will be 15, which may exceed 50 persons requiring a second means of egress from the space. 

 

Interior finish

Please indicate the required interior floor, wall and ceiling finish according to the Business occupancy chapter.   Provide specification sheets for the finishes if available.  If not have them available on site for the inspector. 

 

INFORMATIONAL ONLY NO RESPONSE NECESSARY:
The system(s) outlined in this set of plans is conceptual.

A HOLD has been placed at framing (105) until either: a) a permit has been pulled or b) a letter submitted from respective system contractor indicating no work to be done to the existing system:
- fire alarm system
- fire sprinkler system