Clearance Sheet C2019-003178

 Department IssuesSigned OffIntl

Plan reviewed for a new underground line running to building J.  This line consists of approximately 55' of 8" DR14 ending with an 8"x6" tee capped on one side.  The other side of the tee has approximately 10' of 6" DR14 continuing to 1' AFF.  Reviewed using FFPC 6th edition effective Dec. 31, 2017.

Plans APPROVED 10/18/19 JSB

Reviewer: 
Joseph Branton 904-209-1721
 

Please call 904-209-1740 press 1, then press 2 to schedule a fire inspection BEFORE cover-up.

INFORMATIONAL: Your permit fee includes the cost of review, one hydrostatic test inspection and one final inspection. If you will require more than one hydro/visual inspection you will need to call 209-1740 x 1 to arrange payment.
  

Review by the AHJ shall not relieve the applicant of the responsibility for compliance with the Code.

10/18/2019 jbranton
Informational

Make sure:
- The top of the pipe shall be buried not less than 2 1/2 ft (0.8 m) to prevent mechanical damage.24:10.4.3
- Pipe under driveways shall be buried at a minimum depth of 3 ft (0.9 m). 24:10.4.4
- Any aboveground pipe (including backflow) is protected against freezing. 24:10.5.1

10/18/2019 jbranton