Clearance Sheet C2019-001625*001

 Department IssuesSigned OffIntl

Plan reviewed for new ANSUL R-102 3 Gallon, UL EX 3470, UL 300 compliant suppression system protecting a 14' hood with 2 14" diameter ducts and from left to right: Garland US Range SUMG-200 gas convection oven, Garland G Series 36" 6 burner gas range, Garland Model GD-24RB Gas Broiler and Cleveland Steam Craft Ultra 3 countertop electric steamer. 11 Flow Points available, 9 Flow Points used.

Reviewed using FFPC 7th edition effective Dec. 31, 2020. NFPA 1 and 101 references are Florida Editions of the code in the FFPC.

Reviewer: D. Feagle 904-209-1721, dfeagle@sjcfl.us

To schedule fire inspections please call 827-6842 (automated system). Questions about inspections please call 209-1740x1.
Review by the AHJ shall not relieve the applicant of the responsibility for compliance with the Code.  

-------------------------------

INSPECTOR NOTE: SEE COMMENTS 1 AND 2.

3/22/2022 dfeagle

RESUBMITTING:
A. Make necessary changes and resubmit everything in person to the Permit Center.
B. Once at the Permit Center swap out altered pages in EACH plan set (job and office). One copy of the removed/old pages will need to be resubmitted and labeled "OLD". Do not forget to remove pages for work not associated in this permit.
C. Provide a response to comments along with any supporting documentation.  Response to comments is REQUIRED not optional.
- The response to comments sheet will need to include a response to each numbered comment and tell us where in the plans the comment was addressed. Ex - "top left of page A11" or "Page E1 note 8".
- Code responses shall reference Florida Fire Prevention Code 7th Ed. (not Building Code)

3/22/2022 dfeagle

1) ANSUL manual provided is an incomplete ANSUL R-102 Restaurant Fire Suppression Manual dated 10-01-02, 04/01/06, etc. The current ANSUL R-102 Restaurant Fire Suppression Manual is dated 2014 - SEPT-01 Rev. 11 as provided by ANSUL. The current edition of the manual was used to conduct the review.

The 2014-SEPT-01 edition of the manual will be required to be provided at time of the Fire Final to receive an approval.

-----------------------------------

Tuesday, March 22, 2022 0745 hrs. DF: I spoke with Gordon Crawford regarding this comment. He has agreed to provide a complete 2014 edition of the manual at time of the fire final for the Inspector.

3/22/2022 dfeagle

2) Plans do not indicate an electrical shunt for the Cleveland Electric Steam Generator.

Provide the listed electrical disconnect. This will be verified by the Fire Inspector at time of the fire final.

-----------------------------------

Tuesday, March 22, 2022 0745 hrs. DF: I spoke with Gordon Crawford regarding this comment. He will provide the electrical disconnect.

3/22/2022 dfeagle