SJC Home
Clearance Sheet C2019-001625*001

 Department IssuesSigned OffIntl

1)INFORMATION HOLD PLACED AT INSPECTION 102 (SLAB) 2-SETS OF APPROVED TRUSS ENGINEERING

1/8/2021 jadams

2)INFORMATION HOLD PLACED AT 100(COMPLETE ROUGH)MANUFACTURED SPECS.ON SAUANA SHOWING COMPLIANCE WITH SECTION 914 FBC MECHANICAL

1/8/2021 jadams

1)INFORMATION GENERATOR REQUIRES A SEPERATE PERMIT

1/8/2021 jadams

4) PROVIDE LARGER TO SACLE DRAWING OF MAIN ELECTICAL ROOM SHOWING LOCATION OF DISCONECT AND CLEARENCES OF PANELS

1/8/2021 jadams

3) NEED FIRE SERVICE APPROVAL

1/8/2021 jadams