SJC Home
Clearance Sheet C2018-002137

 Department IssuesSigned OffIntl

Plans for a 75 head Wet NFPA 13 sprinkler system for a new Verizon store.  The plans were reviewed using the 2013 edition of NFPA 13.  The plans are REJECTED for the following reasons:

 

The remote area submitted differs from what the EOR for the sprinkler system has called out.  Please provide revised plans, revised criteria, or seek a new engineer in accordance with the requirements set forth in 61G-15. 

Florida Administrative Code (FAC) 61G15-32.002 defines a material deviation as "Any deviation from the design parameters established and documented by the Engineer of Record." Furthermore FAC 61G15-32.003(6) states "When layout documents contain material deviation from the Engineer of Record's Fire Protection System Engineering Document, such layout documents are not compliant unless they are accompanied by revised Engineering Documents made and sealed by the Engineer of record for the Fire Protection System."

 

Please note that the FDC will be required to be a freestanding FDC as provided on the approved DRC site plan.  Please make this change on the plans.