| | Department Issues | Signed Off | Intl |
|
|
1. Missing Code Analysis
Please provide a code analysis for this project, listing such items as Type of Construction, Use classification, Occupant load, Occupant Load, Sprinklered or non-sprinlered etc...
|
2/26/2015
| wfreeman |
|
|
2. Missing Life Safety
Please provide life safety information, such as occupant load, travel distance, number of exits, means of egress, exit lighting and fire extinguisher locations.
|
2/26/2015
| wfreeman |
|
|
3. Missing Ventilation
Please provide minimum ventilation per FBC-Mechanical, table 403.3
|
2/26/2015
| wfreeman |
|
|
4. Incomplete Electrical
The plans appear to indicate a second service being installed on a building with an existing service. NEC 230.2 does not permit this. please provide a revised riser diagram indicating how the newly installed 200 amp subpanel will be supplied by the existing service. Please provide a panel schedule for the new subpanel. Please indicate the current service size and provide electrical calculations to verify the existing service can handle the new loads from the new addition. Please clarify if the existing service is single phase or 3 phase.
|
2/26/2015
| wfreeman |
|
|
General Notes: Your re-submittal shall include two complete sets of plans. Please insert the revised pages into the plan sets, and pages removed from the stamped "Job copy" set, shall be marked as "old set" and shall be included in the re-submittal. If old "Job copy" drawings, are not resubmitted there will be additional plan review fee charged due to the amount of time necessary to review entire drawing again. ALL ITEMS changed or revised on plans and documents shall be identified by circling, clouding or identified by some other legible method. ADDITIONAL ITEMS MAY BE REQUIRED - DEPENDING ON INFORMATION AND CLARITY OF FINAL PLANS SUBMITTED FOR REVIEW.
|
2/26/2015
| wfreeman |