Clearance Sheet C2012-001554

 Department IssuesSigned OffIntl
Please provide site specific available Fault Current Letter from utility company as per NEC 2008 Section 110.9.

10/10/2012 A hold will be placed.
10/10/2012 ccrain

Please revisit the occupancy classification of this project and apply all applicable requirements to the new occupancy classification.

10/10/2012 ccrain

Please provide the manual N and manual D to complete the energy package.

10/10/2012 ccrain

An electrical service disconnect must be provide at the exterior of the building or the service meter can and panel must be back to back. 

10/10/2012 ccrain

Please provide the metal building sealed shop drawings that are to be review by engineer of record.

10/10/2012 A hold will be placed on the 105 inspection for sealed shop drawing review by the engineer of record.

10/10/2012 ccrain

Need current product approval number for store front.

10/10/2012 ccrain

Please state the R-value of the roof area that is to be the building envelope.

10/10/2012 ccrain