Clearance Sheet C2009-000356*007

 Department IssuesSigned OffIntl

#1

sheet t1.0 lists bldg. type3b / 2nd sheet t1.0 lists type 2b ?

8/19/2015 fbecza

#2

separate unit build-outs require separate permits / units 204 & 205 now one unit , 208 & 209 separate units

8/19/2015 fbecza

#3

per fbc 507.1 doors in unit 204 / 205 cannot reduce the width of egress by more than half

8/19/2015 fbecza

#4

show both panels for units 208 & 209 on power riser diagram

8/19/2015 fbecza

#5

panels 'a' and 'pp1' circuit layouts not similar 2 ahu's and 2 water heaters on same panel in separate units 208 & 209

8/19/2015 fbecza

#6

need summary of work to be done in units 204 & 205 with code summary of combined units

8/19/2015 fbecza

#7

provide written response to all review comments

8/19/2015 fbecza