Clearance Sheet C2007-001882

 Department IssuesSigned OffIntl

Plans for building fire alarm system.  Most issues have been addressed, however we are still awaiting a sealed letter from the engineer permitting the beam detector substitution.  FAC 61G15-32.003.  I held the plans as long as I could.  Plans REJECTED.