INFORMATIONAL ONLY NO RESPONSE NECESSARY:
The system(s) outlined in this set of plans is conceptual.
A HOLD has been placed at framing (105) until either: a) a permit has been pulled or b) a letter submitted from respective system contractor indicating no work to be done to the existing system:
- fire alarm system
- fire sprinkler system
Friday, March 29, 2019 I signed off sprinkler hold since Mr. Law was here yesterday speaking with Reviewer Webb. He told reviewer Webb no sprinkler or fire alarm work needed to be done and the interior finish in av room was all sheetrock. Reviewer Webb forgot to sign off sprinkler hold also.