SJC Home
Clearance Sheet C2007-000692*001

 Department IssuesSigned OffIntl

Plan is for approximately 3300 sq ft awning on the 2nd floor of 3 story bldg. The use under this awning will be dining and a bar area and is required to be protected by automatic fire sprinklers. This was reviewed under 2004 Fl Fire Prevention Code. These plans are rejected.

Please provide documentation the framing will hold fire sprinkler system.

 
NFPA 101,11.9.1.2 states that all membrane roofs shall be fire resistance and 11.9.1.6.1 states that fabrics shall be fire resistance in accordance with NFPA 101,10.3.1 Provide documentation.