SJC Home
Clearance Sheet C2007-000576

 Department IssuesSigned OffIntl

These are revised plans to address previous comments.

All comment have been addressed except for 2 section of the fire alarm design criteria. (we will place a hold on the BP and no inspection past slab until c & e of the design criteria is submitted.

Plans are approved with the following notes added to the plans:

1. Page A23,

- the occupant load was slightly increased to account for the net lobby area, the additional 176 persons did not effect the exits shown on the plans.

- The emergency lighting is subject to final inspection Please look at the photometric study provided on page E-8.

2. Page A19 & 20 Interior Finish, the plans set has the rating for Class A or B, however at the final please have the contractor provide the inspector with a copy of the documentation of Class A or B for the finishes in question.

3. PAge 19, Per the architect the Stove was removed.

4. Page FA 1.1, the sealed fire alarm design criteria was missing response to c & e of the 61G15-33.006. This information will need to sealed and provided to the building & fire department before we can totally approve the plans. We will be placing a hold on the building permit which will allow you to pour the slab but no additional inspections will be authorized.

5. the following holds for additional permits have been placed on the Building Permit. No inspection past slab will be allowed until these permit are approved.

Fire Sprinkler
Fire Alarm