There is a correction for the previous issues report:
The building is protected with a fire sprinkler system.
The re submittal addressed the previous comments and the plans can be approved.
Note:
1. The interior finish information is in a separate folder with the plans.
2. The product review of heat production products is being compiled. based on verbal conversation with the product technical section there are no vent requirements. The hard copies of reports will be placed in the product file for dunkin donuts that will verify this.
3. A Separate FIRE SPRINKLER permit will be required for the modification to the existing fire sprinkler system. A hold will be placed on the building permit and no inspections will be done until this permit is submitted & approved.