| | Department Issues | Signed Off | Intl |
|
|
FYI - NEED FAULT CURRENT LETTER FROM THE POWER COMPANY NOT A CONSULTING ENGINEER BEFORE ELECTRICAL PERMIT CAN BE ISSUED.
|
| |
|
|
PRESCRIPTIVE ENEVOLPE OF ENERGY FORM MUST PASS ON THE ORIGINAL SIGNED & SEALED ENERGY CALCULATION FORM
|
| |
|
|
HIGHEST TRUSS IN PACKAGE DOES NOT MEET ARCHITED MEAN ROOF HIGHEST OF 36FT WHY?
|
| |
|
|
ALL TRUSS ENGINEERING SHEETS NEED THE SIGNATURE OF DESIGN ENGINEER ON THEM NOT JUST HIS RAISED SEAL
|
| |
|
|
WHERE IS THE REQUIRED TRUSS COPIES OF TRUSS LAYOUT SHEET WITH ALL TRUSSES LABELED?
|
| |