FYI - NEED FAULT CURRENT LETTER FROM THE POWER COMPANY NOT A CONSULTING ENGINEER BEFORE ELECTRICAL PERMIT CAN BE ISSUED.  
PRESCRIPTIVE ENEVOLPE OF ENERGY FORM MUST PASS ON THE ORIGINAL SIGNED & SEALED ENERGY CALCULATION FORM  
HIGHEST TRUSS IN PACKAGE DOES NOT MEET ARCHITED MEAN ROOF HIGHEST OF 36FT WHY?  
ALL TRUSS ENGINEERING SHEETS NEED THE SIGNATURE OF DESIGN ENGINEER ON THEM NOT JUST HIS RAISED SEAL  
WHERE IS THE REQUIRED TRUSS COPIES OF TRUSS LAYOUT SHEET WITH ALL TRUSSES LABELED?