SJC Home
Clearance Sheet C2004-005747

 Department IssuesSigned OffIntl
These plans are for the fire sprinkler system fo a 4 story building with a conbustable roof. For the most part the plans look good, however there is a question as to the responsibility of the underground to this system & the identification of the new change in the law that requires the underground to terminate 1' above finish floor. Based on this and a conversation with the contractor, the contractor has requested that the plans be returned to be corrected then resubmitted.