Clearance Sheet C2003-005489*001

 Department IssuesSigned OffIntl
1) Provide a complete framing plan for the walls and ceiling, including bearing walls, headers, insulation, wall section etc. The floor/ceiling must be designed for min 125# PSF if for storage. 6/5/04 If the space above the office(s) not to be used for storage, MUST state on the plans "No storage" and post "NO storage" signs in area, before final inspection. No deck allowed above the office space except for minimun space for required for the air handler.  
2) Need the CFM for the restroom exhaust fan. 6/5/2004 CFB
3) Provide a complete electrical drawings for this unit, including the service entrance conductors, riser diagram, main disconnect, panel schedule. etc.  
4) Where is the required service sink and HiLo drinking fountian?  
5) Must provide the clear inside dimenisions of the H/C restrooms. 6/5/2004 CFB
The Building Valuation increase is based on the data compiled by SBCCI & ICC using the Marshall Valuation Service as published by the Marshall and Swift Publication Company and printed in the Southern Builder.  
6) The drawing has a 4 ton HVAC unit, the energy form that was submitted has a 5 ton unit. The energy form and the drawings must match. Which will be correct?