SJC Home
Clearance Sheet C2003-002286*002

 Department IssuesSigned OffIntl
Provide the structual schedule in larger print. (size of notes is OK)  
Must have a smoke detector inside each bedroom. (NFPA-72)  
Must submit an approved DRC site plan  
Provide a completed DRC clearance sheet for this project.  
Provide water/sewer availability letters.  
Provide the Fault Current Letter from the power company. No electrical permits will be issued until submitted and approved.  
The Notice of Commencement must be submitted to the building dept. prior to any inspections.  
Provide the engineering for the precast lintels to be used and the mininum bearing.  
Must provede the information listed in FBC 104.2 and 1606.1.7 (5).Provide the information for the windows to comply with the code, note that this building is located in the wind-borne debris area and will require impact-resistance glass or engineered shutters.  
Provide two (2) sets of truss drawings with a layout sheet. The layout sheet to be signed by the structual engineer of record that he/she has reviewed the truss drawings and they meet his/her design requirements. Include a schedule for the uplift connectors required including number of fasteners for each connector.  
The Building Valuation increase is based on the data compiled by SBCCI & ICC using the Marshall Valuation Service as published by the Marshall and Swift Publication Company and printed in the Southern Builder.