Clearance Sheet C2000-000128*001

 Department IssuesSigned OffIntl

Please provide a total occupant load for occupancy and address the additional plumbing facilities that may be needed because of the additional occupant load.

 

Clearance sheet calls for a DEP permit. 

 

Please provide a current ESR report for the foam insulation that is to be used. 

 

Please provide over framing details for roof area extending over existing roof.

 

Please address proper roof truss connections, masonry beam to wood truss.

 

Unable to locate on the plans the plywood thickness.

 

Please address the wind exposure category for the location of structure.