SJC Home
Clearance Sheet R2015-001980

Clearance Sheet is Over 180 Days

Contractor: KELLER, JAMES A
Unpaid $0.00(); Paid $401.50(0785931)
Cert Occ
Proj Name: Parcel:
Prop Use Desc: Prop Use:
Contractor ID: Valuation:

Pre:      Street Num:      Street:      Class:      Post:      Zip  Supplemental:   


Expedited Review Required:   

Permit #Issue DateInfoContractorPaidDueAssocInfo
21503638 8/12/2015 8:42:04 AMU FPL3.05 JONES JR, JOHN W.00[ MAIN SERVICE PANEL Amps 200 - TEMPORARY POLE 1 - ]
31502939 8/27/2015 11:20:08 AM MCCRARY, FRANKLIN W.00[ NEW CONSTRUCTION 19 - ]
41506124 9/29/2015 3:54:55 PMA WILSON, TODD BECKETT00[ NEW HVAC Valuation 7400 - ]
41506521 10/15/2015 1:35:56 PMG TIPTON, RONALD00[ GAS PIPING Outlets 3 - ]
81600247 2/1/2016 11:44:25 AM HANEY, JONATHAN00[ SPRINKLER HEADS Units 30 - ]
11506828 8/6/2015 12:16:26 PM101KELLER, JAMES A00 


Log

TypeRcv DtPln Rvwd DtRvwdByStatusCommentOutstanding CommentsPlan Review
BLDG PLAN REVIEWER7/16/2015 abutler7/24/2015 jdacostajdacostaRejected 9 Plan Review
BLDG RESUBMIT8/5/2015 krobshaw8/5/2015 jdacostajdacostaApproved With holds for duct leakage test. 0 Plan Review
BLDG REVISION1/21/2016 brepult1/21/2016 jdacostajdacostaRejected DUCT LEAKAGE TEST, CHANGE OF ENERGY SHEETS TO SATISFY DUCT LEAKAGE 1 Plan Review
BLDG REVISION1/22/2016 ehumphreys1/22/2016 jdacostajdacostaApproved REVISION RESUB. Revision Fee $40. 0 Plan Review
PENDING PERMIT ISSUES2/10/2016 krobshaw2/10/2016 jdacostajdacostaApproved FINISHED CONSTRUCTION FEMA FORM. House sited solely in the X Zone. 0 Plan Review


Notes

Note DtNote
1/22/2016 ehumphreys

APPROVED REVISION PICKED UP BY KELLER

1/21/2016 krobshaw

REJECTED REVISION ON SHELF

7/24/2015 ehumphreys

REJECTED PLAN ON SHELF