Clearance Sheet R2015-001980 |
|
|
Clearance Sheet is Over 180 Days
|
Contractor:
KELLER, JAMES A |
|
|
Unpaid $0.00(); Paid $401.50(0785931)
|
|
Cert Occ |
|
|
Proj Name: |
|
Parcel: |
|
|
Prop Use Desc: |
|
Prop Use: |
|
|
Contractor ID: |
|
Valuation: |
|
Pre:
Street Num:
Street:
Class:
Post:
Zip
Supplemental:
Expedited Review Required:
|
21503638
| 8/12/2015 8:42:04 AM | U FPL3.05 | JONES JR, JOHN W. | 0 | 0 | [ MAIN SERVICE PANEL Amps 200 - TEMPORARY POLE 1 - ] |
|
31502939
| 8/27/2015 11:20:08 AM | | MCCRARY, FRANKLIN W. | 0 | 0 | [ NEW CONSTRUCTION 19 - ] |
|
41506124
| 9/29/2015 3:54:55 PM | A | WILSON, TODD BECKETT | 0 | 0 | [ NEW HVAC Valuation 7400 - ] |
|
41506521
| 10/15/2015 1:35:56 PM | G | TIPTON, RONALD | 0 | 0 | [ GAS PIPING Outlets 3 - ] |
|
81600247
| 2/1/2016 11:44:25 AM | | HANEY, JONATHAN | 0 | 0 | [ SPRINKLER HEADS Units 30 - ] |
|
11506828
| 8/6/2015 12:16:26 PM | 101 | KELLER, JAMES A | 0 | 0 | |
Log
| BLDG PLAN REVIEWER | 7/16/2015 abutler | 7/24/2015 jdacosta | jdacosta | Rejected |
| 9 |
Plan Review
|
| BLDG RESUBMIT | 8/5/2015 krobshaw | 8/5/2015 jdacosta | jdacosta | Approved |
With holds for duct leakage test.
| 0 |
Plan Review
|
| BLDG REVISION | 1/21/2016 brepult | 1/21/2016 jdacosta | jdacosta | Rejected |
DUCT LEAKAGE TEST, CHANGE OF ENERGY SHEETS TO SATISFY DUCT LEAKAGE
| 1 |
Plan Review
|
| BLDG REVISION | 1/22/2016 ehumphreys | 1/22/2016 jdacosta | jdacosta | Approved |
REVISION RESUB. Revision Fee $40.
| 0 |
Plan Review
|
| PENDING PERMIT ISSUES | 2/10/2016 krobshaw | 2/10/2016 jdacosta | jdacosta | Approved |
FINISHED CONSTRUCTION FEMA FORM. House sited solely in the X Zone.
| 0 |
Plan Review
|
Notes
| 1/22/2016 ehumphreys |
APPROVED REVISION PICKED UP BY KELLER
|
| 1/21/2016 krobshaw |
REJECTED REVISION ON SHELF
|
| 7/24/2015 ehumphreys |
REJECTED PLAN ON SHELF
|
|
|