SJC Home
Clearance Sheet R2007-002537*001

Clearance Sheet is Over 180 Days

Contractor: LANNI, WILLIAM FORREST
Unpaid $0.00(); Paid $134.06(01159634)
Cert Occ
Proj Name: Parcel:
Prop Use Desc: Prop Use:
Contractor ID: Valuation:

Pre:      Street Num:      Street:      Class:      Post:      Zip  Supplemental:   


Expedited Review Required:   

Permit #Issue DateInfoContractorPaidDueAssocInfo
22104764 5/21/2021 10:15:57 AMO FPL3.05 JONES, TREVOR J00[ MAIN SERVICE PANEL Amps 200 - TEMPORARY POLE 1 - ]
32104097 6/17/2021 2:48:53 PM VALDES, JOHN O.00[ NEW CONSTRUCTION 15 - ]
42112949 10/4/2021 1:48:23 PMA FOX, GARY A00[ NEW HVAC Valuation 550 - ]
42116154 12/17/2021 3:06:17 PMG LATRONICO, MICHAEL A.00[ GAS PIPING Outlets 4 - ]
12117172 10/27/2021 2:33:27 PM435LANNI, WILLIAM FORREST00 
12100842 3/29/2021 1:01:12 PM101LANNI, WILLIAM FORREST00 


Log

TypeRcv DtPln Rvwd DtRvwdByStatusCommentOutstanding CommentsPlan Review
BLDG PLAN REVIEWER12/10/2020 flundy12/21/2020 hkahlerhkahlerRejected 0 Plan Review
BLDG RESUBMIT1/20/2021 khanson1/20/2021 hkahlerhkahlerApproved 0 Plan Review
PENDING PERMIT ISSUES6/25/2021 bbonfanti6/29/2021 hkahlerhkahlerApproved COMPACTION TEST REQUIRED. 0 Plan Review
BLDG REVISION11/2/2021 bmsmith11/2/2021 hkahlerhkahlerRejected METAL ROOF TO ASPHALT SHINGLES ROOF, FIBERGLASS INSULATION TO ICYNENE OPEN CELL FOAM 0 Plan Review
BLDG REVISION12/9/2021 bmsmith12/13/2021 hkahlerhkahlerRejected ADD WOOD DECK TO REAR OF THE HOME NEW ENERGY CALCS; CHANGE FROM METAL ROOF TO ARCHITECTURAL SHINGLE, CHANGE FROM FIBERGLASS INSULATION TO LCYNENE INSULATION 1 Plan Review
BLDG RESUBMIT12/20/2021 ehumphreys12/21/2021 hkahlerhkahlerApproved REVISION RESUBMITTAL// NEW ENERGY CALCS; CHANGE FROM METAL ROOF TO ARCHITECTURAL SHINGLE, CHANGE FROM FIBERGLASS INSULATION TO LCYNENE INSULATION 0 Plan Review
BLDG REVISION12/21/2021 hkahler12/21/2021 hkahlerhkahlerRejected Add a new deck to rear of home. Add Stairs to Foundation "B". 1 Plan Review
BLDG REVISION1/7/2022 ehumphreys1/10/2022 hkahlerhkahlerApproved RESUBMITTAL 0 Plan Review


Notes

Note DtNote
  rejected REVISION IN DRAWER under LANNI AWAITING UPDATED CS // emailed issues report
  rejected revision, METAL ROOF TO ASPHALT SHINGLES ROOF, FIBERGLASS INSULATION TO ICYNENE OPEN CELL FOAM, in drawer, em
  rejected revision in drawer, add wood deck, em
  EMAILED REJECTED REVISON IN REJECTED DRAWER UNDER LANNI
  EMAILED REJECTED REVISON IN REJECTED DRAWER UNDER LANNI EMAILED COMMENTS
  EM,Approved Revision in drawer under Lanni,REVISION RESUBMITTAL// NEW ENERGY CALCS; CHANGE FROM METAL ROOF TO ARCHITECTURAL SHINGLE, CHANGE FROM FIBERGLASS INSULATION TO LCYNENE INSULATION & Add a new deck to rear of home. Add Stairs to Foundation "B".