Permit #Issue DateInfoContractorPaidDueAssocInfo
11707974 7/31/2017 10:24:53 AM335CAMPBELL, DON00 


Log

TypeRcv DtPln Rvwd DtRvwdByStatusCommentOutstanding CommentsPlan Review
BLDG PLAN REVIEWER11/18/2016 jdacosta11/18/2016 jdacostajdacostaRejected 4 Plan Review
BLDG RESUBMIT6/14/2017 ehumphreys    4 Review Pending


Notes

Note DtNote
  PLANS FOR 12 X 50 DECK ON HURRICANE MATTHEW SHELF AWAITING CLEARANCE SHEET AND EVALUATION
  SWO placed work commenced prior to permit issuance: see images
  REJECTED PACKAE ON SHELF, EMAILED 11/18
  REJECTED PLAN ON SHELF, AWAITING ENGINEERING AND DEP EMAILED 1/3/16
  CALLED MR CAMPBELL, HE STATES HE WOULD CHECK ON THIS TODAY AND GIVE US A CALL BACK, I ALSO EMAILED THE COMMENTS AGAIN.
  If these plans are for the screen room and the deck, this is a carpentry contactor. Don Campbell.
  PLANS CHECKED OUT TO DON CAMPBELL FOR MEETING WITH TDOYLE/DKING
  PLAN PACKET RETURNED BY DC. AWAITING ENGINEERING/NEW CLEARANCE SHEET. PLANS ON REJECTED SHELF
  PLANS ON LACYS DESK CAN NOT PICK THIS UP UNTIL THE SCREEN ROOM IS PERMITTED