Clearance Sheet M2021-008010*002 |
|
|
Clearance Sheet is Over 180 Days
|
Contractor:
IONELLI, RICHARD L JR |
|
|
Unpaid $0.00(); Paid $0.00()
|
|
Cert Occ |
|
|
Proj Name: |
|
Parcel: |
|
|
Prop Use Desc: |
|
Prop Use: |
|
|
Contractor ID: |
|
Valuation: |
|
Pre:
Street Num:
Street:
Class:
Post:
Zip
Supplemental:
Expedited Review Required:
|
22111777
| 12/8/2021 3:48:01 PM | U FPL4.03 | ADKINS, VIRGIL M | 0 | 0 | [ MAIN SERVICE PANEL Amps 1600 - TEMPORARY POLE 1 - ] |
|
32108054
| 1/31/2022 10:04:58 AM | | POWELL JR, DOUGLAS T | 0 | 0 | [ NEW CONSTRUCTION 227 - ] |
|
42116512
| 12/20/2021 2:53:03 PM | A | FIORE, PATRICK J | 0 | 0 | [ NEW HVAC Valuation 26000 - ] |
|
62200016
| 1/11/2022 8:37:39 AM | SPKL | RAULERSON, WEAVER E II | 0 | 0 | [ SPRINKLER SYSTEM unit 319 - ] |
|
62200229
| 4/18/2022 8:10:54 AM | ALRM | WORTH, ROBERT CORTLAND | 0 | 0 | [ FIRE ALARM Devices 113 - ] |
|
12116714
| 10/25/2021 3:48:39 PM | 105 | IONELLI, RICHARD L JR | 0 | 0 | |
Log
| FIRE MARSHALL REVIEW | 6/10/2021 kdlong | 6/10/2021 kdlong | | Pending |
Prelim Review
| 0 |
Plan Review
|
| BLDG PLAN REVIEWER | 6/16/2021 dfeagle | 6/17/2021 jadams | jadams | Rejected |
Preliminary Review
| 7 |
Plan Review
|
| FIRE MARSHALL REVIEW | 6/16/2021 dfeagle | 6/16/2021 dfeagle | dfeagle | Rejected |
Preliminary Review
| 26 |
Plan Review
|
| FIRE RESUB MARSHAL REVIEW | 9/2/2021 dlyons | 9/2/2021 dlyons | | Pending |
| 26 |
Plan Review
|
| FIRE RESUB MARSHAL REVIEW | 9/28/2021 dfeagle | 9/29/2021 dfeagle | dfeagle | Rejected |
Preliminary ReSubmittal
| 10 |
Plan Review
|
| BLDG RESUBMIT | 9/29/2021 dfeagle | 9/30/2021 jadams | jadams | Rejected |
Preliminary ReSubmittal
| 5 |
Plan Review
|
| BLDG RESUBMIT | 10/11/2021 jadams | 10/11/2021 jadams | jadams | Rejected |
| 3 |
Plan Review
|
| BLDG RESUBMIT | 10/18/2021 jadams | 10/18/2021 jadams | jadams | Approved |
| 0 |
Plan Review
|
| FIRE RESUB MARSHAL REVIEW | 10/18/2021 jadams | 10/18/2021 agedris | agedris | Approved |
Approved with HOLDS for MULTIPLE revisions
| 0 |
Plan Review
|
| FIRE SPRINKLER SYSTEM | 12/10/2021 dlyons | 1/6/2022 dfeagle | dfeagle | Approved |
| 0 |
Plan Review
|
| FIRE MARSHAL REVISION | 12/21/2021 lnewton | 1/5/2022 dfeagle | dfeagle | Rejected |
Revision to remove hold
| 3 |
Plan Review
|
| BLDG REVISION | 1/5/2022 dfeagle | 1/7/2022 jadams | jadams | Approved |
| 1 |
Plan Review
|
| FIRE ALARM SYSTEM | 2/7/2022 dlyons | 2/17/2022 dfeagle | dfeagle | Rejected |
| 7 |
Plan Review
|
| | 2/11/2022 dfeagle | 2/11/2022 dfeagle | dfeagle | Approved |
| 0 |
Plan Review
|
| BLDG REVISION | 2/11/2022 dfeagle | 2/14/2022 jadams | jadams | Approved |
| 0 |
Plan Review
|
| | 2/16/2022 dfeagle | 2/16/2022 dfeagle | dfeagle | Rejected |
| 9 |
Plan Review
|
| | 3/29/2022 dlyons | 4/12/2022 aConnell | aconnell | Approved |
| 0 |
Plan Review
|
| FIRE RESUB ALARM SYSTEM | 4/4/2022 dlyons | 4/14/2022 aConnell | aconnell | Approved |
| 0 |
Plan Review
|
| PENDING PERMIT ISSUES | 1/11/2023 kturner | 1/12/2023 jadams | jadams | Approved |
Truss package
| 0 |
Plan Review
|
| FIRE ALARM SYSTEM | 3/7/2023 dfeagle | 3/7/2023 dfeagle | dfeagle | Approved |
BDA// 08/25/23 DFEAGLE: Status changed from "Rejected" to "Approved" to match actual status of the plans/permit at time of review.
| 0 |
Plan Review
|
| FIRE MARSHAL REVISION | 8/14/2023 dlyons | 8/17/2023 dfeagle | dfeagle | Approved |
Added exit signs in breezeways on all 3 floors
| 0 |
Plan Review
|
| BLDG REVISION | 8/18/2023 bmsmith | | | |
Added exit signs in breezeways on all 3 floors
| 0 |
Review Pending
|
| BLDG REVISION | 8/18/2023 bmsmith | 8/21/2023 shillyard | shillyard | Approved |
Added exit signs in breezeways on all 3 floors
| 0 |
Plan Review
|
Notes
| 10/15/2021 cgal |
This Clearance Sheet Has Been Converted From Non Clearance Sheet Number N2021-004731
|
| |
Emailed rejected fire alarm comments 2/17/2022 - Cubby "W" - lln
|
| |
Re-emailed rejected fire alarm comments 3/7/2022 - Cubby "W" - lln
|
| |
truss package approved under bolen
|
| |
Emailed approved fire comments for revision/emergency lights 8/18/2023 - plans sent to bldg. dept - lln
|
| |
EMAILED;APPROVED REVISION IN FOLDED DRAWER UNDER IONELLI
|
| |
06/18/2021- emailed rejected comments, stored in cubby "96" in back hall way. KL
|
| |
Rejected rolled plan on back shelf (5 Apps total)
N21-4734, N21-4729, N21-4730, N21-4731, N21-4732
Emailed rejection comments to BFREEMAN
|
| |
Rejected plans signed out to BFreeman 10/8/21kt
|
|
|