SJC Home
Clearance Sheet C2024-003901

Clearance Sheet is Over 180 Days

Contractor: BROWN, STEVEN T
Unpaid $0.00(); Paid $22,815.31(01593599,1535970)
Proj Name: Parcel:
Prop Use Desc: Prop Use:
Contractor ID: Valuation:

Pre:      Street Num:      Street:      Class:      Post:      Zip  Supplemental:   


Expedited Review Required:   

Permit #Issue DateInfoContractorPaidDueAssocInfo
22410709 12/5/2024 1:47:07 PMU JEA SANDERS, JEFFREY T00[ MAIN SERVICE PANEL Amps 600 - ]
32404477 8/13/2024 12:34:27 PM KENDALL, BRAD DEAN00[ OTHER PL CHRG Total 4 - ]
42502565 3/14/2025 11:18:21 AMA DUNN, MICHAEL JOHN00[ NEW HVAC Valuation 79585 - ]
62500093 3/6/2025 3:34:10 PMSPKLO'BRIEN, SHAWN P00[ SPRINKLER SYSTEM unit 868 - ]
62500094 3/6/2025 3:34:10 PMSPKLO'BRIEN, SHAWN P00[ SPRINKLER SYSTEM unit 1302 - ]
62500095 3/6/2025 3:34:10 PMSPKLO'BRIEN, SHAWN P00[ SPRINKLER SYSTEM unit 868 - ]
62500213 4/14/2025 8:21:16 AMALRMEDDINGS, JOHN B00[ FIRE ALARM Devices 13 - ]
12415428 11/25/2024 4:24:08 PM320SBROWN, STEVEN T00 
12501883 2/12/2025 9:03:39 AM435CPRICE, JOHN BRADFORD00 


Log

TypeRcv DtPln Rvwd DtRvwdByStatusCommentOutstanding CommentsPlan Review
FIRE MARSHALL REVIEW4/22/2024 dlyons5/10/2024 dfeagledfeagleRejected Prelim Review 6 Plan Review
BLDG PLAN REVIEWER7/12/2024 bmsmith7/12/2024 jadamsjadamsRejected PRELIMINARY REVIEW 4 Plan Review
FIRE RESUB MARSHAL REVIEW8/14/2024 dlyons9/5/2024 dfeagledfeagleRejected 10 Plan Review
BLDG RESUBMIT9/6/2024 jcrodriguez9/9/2024 jadamsjadamsRejected 1 Plan Review
FIRE RESUB MARSHAL REVIEW10/18/2024 lnewton11/8/2024 RDowlingrdowlingApproved 0 Plan Review
BLDG RESUBMIT11/8/2024 jcrodriguez11/8/2024 jedwardsjedwardsApproved 0 Plan Review
FIRE SPRINKLER SYSTEM12/10/2024 dlyons1/3/2025 dfeagledfeagleRejected 11 Plan Review
 1/7/2025 lnewton1/10/2025 sschnellenbergersschnellenbergerRejected 5 Plan Review
FIRE MARSHAL REVISION2/4/2025 lnewton2/27/2025 dfeagledfeagleApproved Structural: Removal of Pump Room in Bldg and combined as w/ exterior water tank 0 Plan Review
FIRE RESUB SPRINKLER SYSTEM2/10/2025 dlyons3/6/2025 dfeagledfeagleApproved 3 permit applications included 0 Plan Review
 2/18/2025 dlyons2/24/2025 sschnellenbergersschnellenbergerApproved 0 Plan Review
BLDG REVISION3/3/2025 jcrodriguez3/3/2025 jedwardsjedwardsApproved Structural: Removal of Pump Room in Bldg and combined as w/ exterior water tank 0 Plan Review
FIRE ALARM SYSTEM3/25/2025 dlyons4/10/2025 dfeagledfeagleApproved 0 Plan Review
 4/9/2025 lnewton4/15/2025 jlhatcherjlhatcherApproved REVISION/Changed Stub Ins to 8" 0 Plan Review


Notes

Note DtNote
8/13/2024 dlyo This Clearance Sheet Has Been Converted From Non Clearance Sheet Number N2024-002220
  Emailed rejected fire comments, routed to bldg. dept. 9/6/24 dml
  Emailed rejected Bldg. Dept. comments - Routed plans back to Fire 9/9/24 jr
  Received plans back from bldg. dept. put in box# 110 9/10/24 dml
  Emailed Approved fire Comments 11/8/2024 - Plans routed to Bldg Dept - lln
  Emailed Rejected Sprinkler Comments 1/3/2025 - Cubby "96" - lln
  Emailed Rejected Fire Comments for Underground 1/13/2025 - Cubby "R" - lln
  plans put in box # 96 2/5/25 dml
  Emailed approved fire revision comments, routed to bldg. dept. 2/27/25 dml
  E-MAILED APPROVAL- APPROVED REVISION ON TOP OF REVISION FILING CABINET UNDER BROWN
  Emailed Approved Fire Comments for Underground Revision 4/17/2025 - lln
  Emailed rejected fire comments, routed plans to bldg. dept. 5/10/24 dml
  EMAILED BLD COMMENTS. LEFT FOR FIRE TO REVIEW RESUBMITTAL.
  Received plans back from bldg. dept. put in box # 103 7/15/24 dml
  Valuation reduced from $14,594,790 due to Foundation Only separate permit #12410748