SJC Home
Clearance Sheet C2021-006506

Clearance Sheet is Over 180 Days

Contractor: BEAUSIR, MICHAEL S
Unpaid $0.00(); Paid $2,861.00(01191497)
Cert Occ
Proj Name: Parcel:
Prop Use Desc: Prop Use:
Contractor ID: Valuation:

Pre:      Street Num:      Street:      Class:      Post:      Zip  Supplemental:   


Expedited Review Required:   

Permit #Issue DateInfoContractorPaidDueAssocInfo
22105518 6/4/2021 4:21:30 PMU FPL4.03 SANDERS, JEFFREY T00[ (2) FEEDER SERVICE PANEL Amps 200 - (2) MAIN SERVICE PANEL Amps 1200 - TEMPORARY POLE 1 - ]
22207112 6/10/2022 1:34:41 PMFPL SANDERS, JEFFREY T00[ FEEDER SERVICE PANEL Amps 200 - ]
32103756 6/30/2021 11:20:58 AM RODGERS, ANDREW JASON00[ NEW CONSTRUCTION 8 - ]
32203824 1/1/0001 12:00:00 AM RODGERS, ANDREW JASON00[ NEW CONSTRUCTION 1 - ]
42206548 5/11/2022 10:08:04 AMA BACHMAN, WILLARD JOHN III00[ NEW HVAC Valuation 40000 - ]
42208377 6/13/2022 2:43:14 PMG RODGERS, ANDREW JASON00[ GAS PIPING Outlets 1 - ]
62100280 9/7/2021 11:17:19 AMALRMELKSNIS, DARRYL ANTHONY00[ FIRE ALARM Devices 10 - ]
62100460 12/22/2021 8:01:13 AMSPKLTHOMAS, JOSEPH R00[ SPRINKLER SYSTEM unit 1 - ]
12114699 9/14/2021 8:42:19 AM435CRUSS, MICHAEL L JR00 
12101010 5/6/2021 12:48:07 PM327BEAUSIR, MICHAEL S00 


Log

TypeRcv DtPln Rvwd DtRvwdByStatusCommentOutstanding CommentsPlan Review
FIRE MARSHALL REVIEW12/31/2020 flundy12/31/2020 dfeagle Pending 0 Plan Review
BLDG PLAN REVIEWER1/21/2021 PWebb1/22/2021 jadamsjadamsApproved 0 Plan Review
FIRE MARSHALL REVIEW1/21/2021 PWebb1/21/2021 PWebbpwebbApproved 0 Plan Review
 1/25/2021 SMurray1/25/2021 SMurraysmurrayRejected 1 Plan Review
 2/1/2021 SMurray2/1/2021 SMurraysmurrayApproved FDC on BFP 0 Plan Review
FIRE MARSHAL REVISION7/23/2021 kdlong7/23/2021 kdlong Pending 0 Plan Review
FIRE ALARM SYSTEM7/28/2021 kdlong7/28/2021 dlyons Pending 0 Plan Review
BLDG REVISION8/12/2021 PWebb8/16/2021 jadamsjadamsApproved 0 Plan Review
FIRE MARSHAL REVISION8/12/2021 PWebb8/12/2021 PWebbpwebbApproved 0 Plan Review
FIRE ALARM SYSTEM8/23/2021 dfeagle8/25/2021 dfeagledfeagleApproved 0 Plan Review
FIRE SPRINKLER SYSTEM9/10/2021 dlyons9/10/2021 dlyons Pending 0 Plan Review
FIRE SPRINKLER SYSTEM10/14/2021 PWebb10/14/2021 PWebbpwebbRejected 7 Plan Review
FIRE MARSHAL REVISION10/20/2021 dlyons11/10/2021 PWebbpwebbApproved 0 Plan Review
BLDG REVISION11/10/2021 PWebb11/10/2021 jadamsjadamsApproved 0 Plan Review
FIRE RESUB SPRINKLER SYSTEM12/20/2021 PWebb12/20/2021 PWebbpwebbRejected 6 Plan Review
FIRE RESUB SPRINKLER SYSTEM5/24/2022 lnewton5/25/2022 agedrisagedrisApproved Route to Anthony 0 Plan Review


Notes

Note DtNote
  Emailed rejected sprinkler comments 10/14/21 put in cubby "T" DML
  APPROVED REVISION IN DRAWER UNDER HAWKINS 11/12/21 CS SENT LINK