Clearance Sheet C2019-006448 |
|
|
Clearance Sheet is Over 180 Days
|
Contractor:
MOORE, THEODORE P |
|
|
Unpaid $0.00(); Paid $428.00(01091532,1091856)
|
|
Cert Occ |
|
|
Proj Name: |
|
Parcel: |
|
|
Prop Use Desc: |
|
Prop Use: |
|
|
Contractor ID: |
|
Valuation: |
|
Pre:
Street Num:
Street:
Class:
Post:
Zip
Supplemental:
Expedited Review Required:
|
22000885
| 2/5/2020 4:23:23 PM | FPL | ROCHELL, BUD C | 0 | 0 | [ WIRING # OF RESIDENCES OR SEPARATE UNITS 1 - ] |
|
32000690
| 2/11/2020 10:02:22 AM | | FERGUSON, RALPH | 0 | 0 | [ NEW CONSTRUCTION 17 - ] |
|
42001295
| 2/6/2020 4:30:09 PM | A | PHILLIPS, JOHN EUGENE | 0 | 0 | [ DUCTWORK ONLY VALUATION 17275 - ] |
|
42001475
| 2/12/2020 12:08:08 PM | A | RIX, DAVID F. | 0 | 0 | [ NEW HVAC Valuation 9500 - ] |
|
62000043
| 3/24/2020 2:22:06 PM | SPKL | PEELER, JERRY | 0 | 0 | [ SPRINKLER SYSTEM unit 12 - ] |
|
11915167
| 2/5/2020 9:11:02 AM | 437B | MOORE, THEODORE P | 0 | 0 | |
Log
| FIRE MARSHALL REVIEW | 12/6/2019 kcooper | 12/17/2019 PWebb | pwebb | Approved |
| 0 |
Plan Review
|
| BLDG PLAN REVIEWER | 12/17/2019 PWebb | 12/18/2019 fbecza | fbecza | Approved |
| 0 |
Plan Review
|
| FIRE SPRINKLER SYSTEM | 2/27/2020 kcooper | 3/18/2020 agedris | agedris | Approved |
| 0 |
Plan Review
|
Notes
|
|