Emailed rejected fire comments 2/28/22, routed over to Building for review. DML
|
| |
LARGE ROLLED REJECTED PLANS are located on the gray cart in the corner behind station #2.
|
| |
Emailed Rejected Fire Review Comments 11/20/2023 - Plans were routed to Bldg Dept 11/28/2023 - Previously held per JAdams as they were awaiting Fires Approval, but directed to send per Fire Plan Reviewers - lln
|
| |
APPROVED BY BUILDING; PLANS SENT BACK TO FIRE TO AWAIT REJECTION COMMENTS TO BE ADDRESSED FOR FIRE-BMS
|
| |
Received plans back from Bldg Dept 11/30/2023 - Standing next to hall cubby - Re-emailed Rejected Fire Comments - lln
|
| |
Plans routed over to Bldg. Dept. 12/8/23 dml
|
| |
Emailed rejected underground comments. Plans put in cubby "R" 8/1/24 dml
|
| |
Emailed rejected fire revision comments, plans routed over to bldg. dept. 2/4/25 dml
|
| |
Emailed rejected Bldg. Dept. comments for revision - Revision routed to Fire 2/5/25 jr
|
| |
Received rejected revision back from bldg. dept. plans put in corner by fire exting. cabinet. 2/5/25 dml
|
| |
Emailed rejected fire sprinkler comments, plans put in cubby "S" 2/12/25 dml
|
| |
Emailed approved fire revision comments. Plans routed over to bldg. dept. 3/28/25 dml
|
| |
EMAILED APPROVED REVISION READY FOR PICK UP; IN BREEZYS OFFICE DUE TO SIZE-BMS 03/31/2025
|
| |
Emailed Rejected Fire Comments for BDA 5/6/2025 - Cubby "108" - lln
|
| |
***FEES PAID FOR MAJOR REVSIONS APPROVED 3/28/25*** - PLANS STILL IN BREEZY'S OFFICE FOR PICK UP!!!!
|
| |
Emailed Rejected Fire Comments for Sprinkler 6/13/2025 - Back Hallway "Fire Extinquisher" - lln
|
| |
Emailed Rejected Fire Comments for Revision 6/26/2025 - Revision routed to bldg. Dept - lln
|
| |
EMAILED REJECTED REVISION COMMENTS FROM BLDG-PLANS SENT BACK TO FIRE ET
|
| |
Received Rejected Revision back from bldg. dept 6/27/2025 - Plans in Back Hallway - lln
|
| |
Emailed Rejected Fire Comments for Revision 8/27/2025 - Revision routed to Bldg Dept - lln
|
| |
E-MAILED REJECTION COMMENTS- REJECTED REVISION ROUTED BACK TO FIRE
|
| |
Received Plans back from bldg. dept 8/27/2025 - Back Hallway - lln
|
| |
Emailed approved fire revision comments. Plans routed over to bldg. dept. 11/4/25 hs
|
| |
E-MAILED APPROVAL- APPROVED REVISION ON THE DESK AT STATION 9 UNDER DILLON- 11/5/25 AH
|
| |
emailed revision ready- put with other revision on STATION 9
|
| |
Emailed rejected fire alarm comments, plans put in cubby "D" 11/12/25- hs
|
| |
Emailed approved fire revision comments. Plans routed over to bldg. dept. 2/11/26- hs
|
| |
APPROVED REVISION AT STATION 9.//EMAILED UPDATE
|
| |
Emailed Approved Fire Comments for Revision 3/24/26 - Plans routed to Bldg Dept - hs
|
| |
E-MAILED APPROVAL- APPROVED REVISION IN APPROVED REVISION CABINET ON BOTTOM SHELF UNDER DILLON
|
| |
Emailed Approved Fire Comments for Revision 6/25/26 - Plans routed to Bldg Dept - hs
|
| |
EMAILED REVISION READY FOR PICK-UP; EXTREMELY LARGE SET OF PLANS- PLACED IN COMMERCIAL OVERFLOW NEXT TO CON LICEN PRINTER UNDER -DILLON-
|
| |
EMAILED COMMENTS; LEFT FOR FIRE
|
| |
Received Revision addressing Chemicals & Signage back from bldg. dept 7/9/2026 - Cubby "3" -lln
|