Clearance Sheet # R2022-005088
|
|
|
|
22-044547
|
*FL BCAIB SURCHARGE(468.631)
| | 12210934 | 0.0150 | 618.0300 |
$9.27
|
|
22-044547
|
*FL DBPR SURCHARGE(553.721)
| | 12210934 | 0.0100 | 618.0300 |
$6.18
|
|
22-044547
|
BLDG PERMIT FEE
| | 12210934 | 1.0000 | 703.5600 |
$703.56
|
|
22-044547
|
PERMIT FEE PP REDUCTION
| | 12210934 | -0.6500 | 703.5600 |
($457.31)
|
|
22-044547
|
Permit Issuance Fee
| | 12210934 | 1.0000 | 20.0000 |
$20.00
|
|
22-044547
|
PLAN CHECK FEE
| Ttl Fee $351.78 - Credit $246.24 | 12210934 | 1.0000 | 105.5400 |
$105.54
|
|
22-070369
|
Revision Bldg
| CHANGED CONTRACTOR | 12210934 | 1.0000 | 53.0000 |
$53.00
|
|
22-044547
|
SOLID WASTE COLLECTION
| 7/1/2022 | 12210934 | 1.0000 | 59.4800 |
$59.48
|
|
22-044547
|
SOLID WASTE RECYCLE
| 7/1/2022 | 12210934 | 1.0000 | 27.7300 |
$27.73
|
|