82203339-805
| IRRGTN |
10/19/2022
|
10/20/2022
| A |
NAZARIO, EDGAR R-10/19 mb review for all finals: mech HVAC, mech gas, plumbing, and electric. All complete and all per plan and code. Results pass
|
|
42202900-408
| GASFNL |
10/19/2022
|
10/20/2022
| A |
-10/19 mb review for all finals: mech HVAC, mech gas, plumbing, and electric. All complete and all per plan and code. Results pass
|
|
42203503-403
| MC FNL |
10/19/2022
|
10/20/2022
| A |
-10/19 mb review for all finals: mech HVAC, mech gas, plumbing, and electric. All complete and all per plan and code. Results pass
|
|
32200631-304
| PL FNL |
10/19/2022
|
10/20/2022
| A |
-10/19 mb review for all finals: mech HVAC, mech gas, plumbing, and electric. All complete and all per plan and code. Results pass
|
|
22207852-204
| EL FNL |
10/19/2022
|
10/20/2022
| A |
-10/19 mb review for all finals: mech HVAC, mech gas, plumbing, and electric. All complete and all per plan and code. Results pass
|
|
12119254-125
| BL FNL |
10/19/2022
|
10/20/2022
| A |
-10/19 mb review for all finals: mech HVAC, mech gas, plumbing, and electric. All complete and all per plan and code. Results pass
|
|
22207852-213
| MTR CN |
8/3/2022
|
8/4/2022
| A |
-08/03 mb- review for meter can in order to power up ac units. Meter set up all ok per code. All slots blanked out in panel except for one 110 ckt and the ac units. All of those circuits are safety off. Result Pass.
|
|
12119254-118
| P LATH |
6/20/2022
|
6/21/2022
| A |
-
|
|
12119254-109
| INSULA |
6/10/2022
|
6/13/2022
| A |
-
|
|
42202900-407
| GS RGH |
6/2/2022
|
6/3/2022
| A |
-06/02 mb- review complete rough- all MEP and dry-in complete- result complete rough: pass with following note: transom windows on back order, and will be reviewed at insulation inspection.
|
|
42203503-401
| MC RGH |
6/2/2022
|
6/3/2022
| A |
-06/02 mb- review complete rough- all MEP and dry-in complete- result complete rough: pass with following note: transom windows on back order, and will be reviewed at insulation inspection.
|
|
32200631-303
| RGH PL |
6/2/2022
|
6/3/2022
| A |
-06/02 mb- review complete rough- all MEP and dry-in complete- result complete rough: pass with following note: transom windows on back order, and will be reviewed at insulation inspection.
|
|
12119254-131
| WINDOW |
6/2/2022
|
6/3/2022
| A |
-6/02 mb- review complete rough- all MEP and dry-in complete- result complete rough: pass with following note: transom windows on back order, and will be reviewed at insulation inspection.
|
|
12119254-105
| FRAMNG |
6/2/2022
|
6/3/2022
| C |
-
|
|
12119254-100
| CM RGH |
6/2/2022
|
6/3/2022
| A |
-06/02 mb- review complete rough- all MEP and dry-in complete- result complete rough: pass with following note: transom windows on back order, and will be reviewed at insulation inspection.
|
|
12119254-106
| RF D&T |
5/5/2022
|
5/6/2022
| A |
-05/05 mb- review plans and site with Rob White. Result 106 Roof, Deck and Ties- Pass
|
|
12119254-116
| RF SHT |
4/22/2022
|
4/22/2022
| A |
-review plans, truss details, and site with Rob White. Today’s inspection is for roof and wall sheathing nailing. This is the first inspection on this house, and the first of many to come on houses in progress. Thus considerable discussion about process, various inspections, product approval codes,
|
|
12119254-117
| P WLLS |
4/22/2022
|
4/22/2022
| A |
-review plans, truss details, and site with Rob White. Today’s inspection is for roof and wall sheathing nailing. This is the first inspection on this house, and the first of many to come on houses in progress. Thus considerable discussion about process, various inspections, product approval codes,
|