SJC Home
Permit # 42207009
ELLIS III, JOHN ELLSWORTH
Permit #AprvDescSchedDtInspDtResultRemarks
82204642-805 IRRGTN 2/7/2023 2/8/2023 A -
42206185-408 GASFNL 2/7/2023 2/8/2023 A NAZARIO, EDGAR R-
42207009-403 MC FNL 2/7/2023 2/8/2023 A NAZARIO, EDGAR R-
32200178-304 PL FNL 2/7/2023 2/8/2023 A -
22208470-204 EL FNL 2/7/2023 2/8/2023 A -
12118773-125 BL FNL 2/7/2023 2/8/2023 A -
22208470-213 MTR CN 12/14/2022 12/13/2022 A -12/13 mb - result pass; meter location safe and complete, panels all blocked off except for AC units and laundry, and those circuit locations with disconnect/ covered receptacles.
22208470-213 MTR CN 12/8/2022 12/9/2022 C -
12118773-109 INSULA 10/14/2022 10/17/2022 A -
12118773-108 LTH NL 10/5/2022 10/6/2022 A -
42206185-407 GS RGH 9/2/2022 9/8/2022 A NAZARIO, EDGAR R-09/08 mb- reviewed whole house for all framing, tie downs, and all trades. Result 106 roof-deck/ties pass, and 100 complete rough pass. Complete rough including rough HVAC, rough gas, rough electric, top out plumbing, and dry in.
42207009-401 MC RGH 9/2/2022 9/8/2022 A NAZARIO, EDGAR R-09/08 mb- reviewed whole house for all framing, tie downs, and all trades. Result 106 roof-deck/ties pass, and 100 complete rough pass. Complete rough including rough HVAC, rough gas, rough electric, top out plumbing, and dry in.
32200178-303 RGH PL 9/2/2022 9/8/2022 A -09/08 mb- reviewed whole house for all framing, tie downs, and all trades. Result 106 roof-deck/ties pass, and 100 complete rough pass. Complete rough including rough HVAC, rough gas, rough electric, top out plumbing, and dry in.
22208470-203 RGH EL 9/2/2022 9/8/2022 A -09/08 mb- reviewed whole house for all framing, tie downs, and all trades. Result 106 roof-deck/ties pass, and 100 complete rough pass. Complete rough including rough HVAC, rough gas, rough electric, top out plumbing, and dry in.
12118773-131 WINDOW 9/2/2022 9/8/2022 A -09/08 mb- reviewed whole house for all framing, tie downs, and all trades. Result 106 roof-deck/ties pass, and 100 complete rough pass. Complete rough including rough HVAC, rough gas, rough electric, top out plumbing, and dry in.
12118773-105 FRAMNG 9/2/2022 9/8/2022 A -09/08 mb- reviewed whole house for all framing, tie downs, and all trades. Result 106 roof-deck/ties pass, and 100 complete rough pass. Complete rough including rough HVAC, rough gas, rough electric, top out plumbing, and dry in.
12118773-100 CM RGH 9/2/2022 9/8/2022 A -09/08 mb- reviewed whole house for all framing, tie downs, and all trades. Result 106 roof-deck/ties pass, and 100 complete rough pass. Complete rough including rough HVAC, rough gas, rough electric, top out plumbing, and dry in.
12118773-117 P WLLS 5/10/2022 5/12/2022 A -review plans and site with Rob White. Results: 116 roof sheathing pass; 107 wall sheathing: pass. Note these are the first inspections at this address…under slab plumbing and slab inspections by SJC.
12118773-116 RF SHT 5/10/2022 5/12/2022 A -review plans and site with Rob White. Results: 116 roof sheathing pass; 107 wall sheathing: pass. Note these are the first inspections at this address…under slab plumbing and slab inspections by SJC.
12118773-107 SHTHNG 5/3/2022 5/4/2022 A - mb - review plans and walk site with Rob White. All wall and roof sheathing properly nailed. All ties and straps per engineering. Result: 107 wall sheathing pass; 116 roof sheathing pass, 106 roof desk and ties pass.
12118773-106 RF D&T 5/3/2022 5/4/2022 A - mb - review plans and walk site with Rob White. All wall and roof sheathing properly nailed. All ties and straps per engineering. Result: 107 wall sheathing pass; 116 roof sheathing pass, 106 roof desk and ties pass.