12205995-125
| BL FNL |
6/24/2022
|
6/24/2022
| A |
-
|
|
32202439-304
| PL FNL |
6/24/2022
|
6/24/2022
| A |
-
|
|
22204521-204
| EL FNL |
6/23/2022
|
6/24/2022
| A |
-
|
|
42205346-403
| MC FNL |
6/23/2022
|
6/24/2022
| A |
NAZARIO, EDGAR R-
|
|
12205995-110
| FIRE W |
6/17/2022
|
6/20/2022
| A |
-06/17 mb- review completed and now stenciled fire wall- result pass. Review for complete rough- rough plumbing should already be passed by Mike, rough electric in walls and ceiling should already be passed by me; today review rough HVAC-and it’s result is pass. Remaining inspections should only be
|
|
32202439-303
| RGH PL |
6/17/2022
|
6/20/2022
| A |
-06/17 mb- review completed and now stenciled fire wall- result pass. Review for complete rough- rough plumbing should already be passed by Mike, rough electric in walls and ceiling should already be passed by me; today review rough HVAC-and it’s result is pass. Remaining inspections should only be
|
|
22204521-203
| RGH EL |
6/17/2022
|
6/20/2022
| A |
-06/17 mb- review completed and now stenciled fire wall- result pass. Review for complete rough- rough plumbing should already be passed by Mike, rough electric in walls and ceiling should already be passed by me; today review rough HVAC-and it’s result is pass. Remaining inspections should only be
|
|
12205995-131
| WINDOW |
6/17/2022
|
6/20/2022
| A |
-06/17 mb- review completed and now stenciled fire wall- result pass. Review for complete rough- rough plumbing should already be passed by Mike, rough electric in walls and ceiling should already be passed by me; today review rough HVAC-and it’s result is pass. Remaining inspections should only be
|
|
12205995-105
| FRAMNG |
6/17/2022
|
6/20/2022
| A |
-06/17 mb- review completed and now stenciled fire wall- result pass. Review for complete rough- rough plumbing should already be passed by Mike, rough electric in walls and ceiling should already be passed by me; today review rough HVAC-and it’s result is pass. Remaining inspections should only be
|
|
12205995-100
| CM RGH |
6/17/2022
|
6/20/2022
| A |
-06/17 mb- review completed and now stenciled fire wall- result pass. Review for complete rough- rough plumbing should already be passed by Mike, rough electric in walls and ceiling should already be passed by me; today review rough HVAC-and it’s result is pass. Remaining inspections should only be
|
|
12205995-120
| P FIRE |
6/6/2022
|
6/7/2022
| A |
-06/06 mb- met with Supt Tim, to review site. All rated walls complete, taped and sealed, and fire caulked. Result Pass. Review for early power (energize/mtr can) : panel complete except for schedule to be reviewed at final, meter bank complete and ground complete. Result pass.
|
|
22204521-213
| MTR CN |
6/6/2022
|
6/7/2022
| A |
-06/06 mb- met with Supt Tim, to review site. All rated walls complete, taped and sealed, and fire caulked. Result Pass. Review for early power (energize/mtr can) : panel complete except for schedule to be reviewed at final, meter bank complete and ground complete. Result pass.
|
|
22204521-212
| ENERGZ |
6/6/2022
|
6/7/2022
| A |
-06/06 mb- met with Supt Tim, to review site. All rated walls complete, taped and sealed, and fire caulked. Result Pass. Review for early power (energize/mtr can) : panel complete except for schedule to be reviewed at final, meter bank complete and ground complete. Result pass.
|
|
12205995-120
| P FIRE |
6/1/2022
|
6/2/2022
| A |
-review 2 hour rated walls on sides of unit, and 1 hr rated wall in storage. All type x placed and nailed, all fire caulk placed. Remaining work to tape and mud bottom half of side walls and all of storage. Result: partial pass.
|
|
32202439-302
| TOPOUT |
5/26/2022
|
5/25/2022
| A |
-
|
|
22204521-210
| P RGHN |
5/23/2022
|
5/23/2022
| A |
-review 2nd layer of 5/8 type x 2 hour rated wall between tenant space on both sides. Result 110 firewall- partial pass. Review rough electric in office and bath walls- Result 210 rough electric- partial pass. Note there will not be any 117 exterior sheathing.
|
|
12205995-117
| P WLLS |
5/23/2022
|
5/23/2022
| C |
-
|
|
42205346-405
| P MECH |
5/20/2022
|
5/19/2022
| A |
NAZARIO, EDGAR R-Result for rough mechanical HVAC- pass.
|
|
12205995-120
| P FIRE |
5/19/2022
|
5/19/2022
| A |
-note this is a rebuild of tenant space in between existing stores. EOR called for metal stud framing against the existing firewall on the adjoining tennant sides. Then to place two layers of 5/8” type x drywall on the inside of those studs. Today first layer placed and nailed. 2nd layer, taping,
|
|
22204521-210
| P RGHN |
5/17/2022
|
5/18/2022
| A |
-Use of either MC or EMT for electric. electric partial pass
|
|
12205995-115
| P FRMG |
5/17/2022
|
5/18/2022
| A |
- Placed, secure Metal studs, to deck. Results: framing partial pass, Discuss requirements for rated wall changes per UL 408. See pictures. Screw pattern to be 8” and 12”.
|
|
12205995-101
| FND/FT |
5/6/2022
|
5/6/2022
| A |
-review prep for slab pour where saw cut. Termite spray, moisture barrier, and proper dowels placed. Result for 102 slab- pass
|
|
42205346-401
| MC RGH |
5/2/2022
|
5/4/2022
| A |
NAZARIO, EDGAR R-met w supt Tim. This is buildout of existing space. Rough Mechanical- supported and sealed- result Partial Pass. Remaining work to insulate all trunk, tie in RTU’s and registers. . Under slab plumbing, all drain in place w head pressure…ready to cover up and then place concrete in saw cuts. Su
|
|
32202439-301
| U/SLAB |
5/2/2022
|
5/4/2022
| A |
-met w supt Tim. This is buildout of existing space. Rough Mechanical- supported and sealed- result Partial Pass. Remaining work to insulate all trunk, tie in RTU’s and registers. . Under slab plumbing, all drain in place w head pressure…ready to cover up and then place concrete in saw cuts. Su
|