12511121-125
| BL FNL |
4/30/2026
|
4/29/2026
| A |
NEWMAN, CODY GAVIN-Building Final Approved
|
|
32504536-304
| PL FNL |
3/31/2026
|
3/30/2026
| A |
-
|
|
42513805-403
| MC FNL |
3/20/2026
|
3/20/2026
| A |
-
|
|
22506949-204
| EL FNL |
3/20/2026
|
3/20/2026
| A |
-
|
|
42513805-403
| MC FNL |
3/17/2026
|
3/17/2026
| D |
-Not ready for inspection
|
|
42513805-000
| INFO |
2/4/2026
|
2/4/2026
| A |
-Ceiling Cover Up
|
|
32504536-000
| INFO |
2/4/2026
|
2/9/2026
| A |
-Passed by FT SUPPLY LINE
|
|
22506949-000
| INFO |
2/4/2026
|
2/4/2026
| A |
-Ceiling cover up
|
|
22506949-212
| ENERGZ |
1/26/2026
|
1/26/2026
| A |
-
|
|
12511121-115
| P FRMG |
1/12/2026
|
1/12/2026
| A |
NEWMAN, CODY GAVIN-Framing on canopy columns
|
|
42513805-401
| MC RGH |
12/30/2025
|
12/30/2025
| A |
-
|
|
32504536-307
| P TPOT |
12/30/2025
|
12/30/2025
| A |
-
|
|
22506949-203
| RGH EL |
12/30/2025
|
12/30/2025
| A |
-final wall coverup. JLS
|
|
22506949-210
| P RGHN |
12/19/2025
|
12/19/2025
| A |
-Restrooms raised floor area, hard ceilings, walls except for area south of passthrough window. JLS
|
|
12511121-000
| INFO.. |
12/19/2025
|
12/19/2025
| A |
HERRINGDINE, CURTIS M-Partial dry-in inspection. Storefront frames only sealed at head, jamb, and sills.
|
|
12511121-109
| INSULA |
12/17/2025
|
12/17/2025
| A |
NEWMAN, CODY GAVIN-
|
|
32504536-302
| TOPOUT |
12/15/2025
|
12/15/2025
| A |
-
|
|
12511121-000
| INFO.. |
12/15/2025
|
12/15/2025
| A |
NEWMAN, CODY GAVIN-
|
|
12511121-109
| INSULA |
12/15/2025
|
12/15/2025
| D |
NEWMAN, CODY GAVIN-
|
|
12511121-115
| P FRMG |
12/15/2025
|
12/15/2025
| A |
NEWMAN, CODY GAVIN-
|
|
12511121-119
| P INSU |
12/10/2025
|
12/10/2025
| A |
NEWMAN, CODY GAVIN-No insulation spray report and insulation not applied to minimum r- value specified
|
|
22506949-210
| P RGHN |
12/4/2025
|
12/4/2025
| A |
-PARTIAL WALL ROUGH FOR EXTERIOR WALLS. JLS
|
|
32504536-308
| P RGH. |
12/4/2025
|
12/4/2025
| A |
-
|
|
12511121-116
| RF SHT |
11/19/2025
|
11/19/2025
| A |
NEWMAN, CODY GAVIN-metal roof underlayment
|
|
12511121-116
| RF SHT |
11/14/2025
|
11/14/2025
| A |
NEWMAN, CODY GAVIN-Main store roof
|
|
12511121-105
| FRAMNG |
11/14/2025
|
11/14/2025
| A |
NEWMAN, CODY GAVIN-main store roof
|
|
12511121-105
| FRAMNG |
11/13/2025
|
11/12/2025
| C |
-Scheduled for the wrong day
|
|
12511121-116
| RF SHT |
11/13/2025
|
11/12/2025
| C |
-scheduled for the wrong day
|
|
12511121-112
| P SLAB |
10/30/2025
|
10/30/2025
| A |
NEWMAN, CODY GAVIN-Interior slab
|
|
32504536-301
| U/SLAB |
10/22/2025
|
10/22/2025
| A |
-
|
|
12511121-104
| BEAMS. |
10/17/2025
|
10/17/2025
| A |
NEWMAN, CODY GAVIN-
|
|
22506949-209
| P USLB |
10/17/2025
|
10/16/2025
| A |
-
|
|
12511121-115
| P FRMG |
10/14/2025
|
10/15/2025
| C |
NEWMAN, CODY GAVIN-
|
|
12511121-111
| P FNDT |
10/14/2025
|
10/13/2025
| C |
-Incorrect permit
|
|
12511121-000
| INFO.. |
10/9/2025
|
10/9/2025
| A |
NEWMAN, CODY GAVIN-Footers for canopy
|
|
12511121-102
| SLAB.. |
9/25/2025
|
9/29/2025
| A |
NEWMAN, CODY GAVIN-
|
|
12511121-103
| LINTEL |
9/26/2025
|
9/29/2025
| A |
NEWMAN, CODY GAVIN-
|
|
12511121-113
| P LNTL |
9/23/2025
|
9/24/2025
| A |
NEWMAN, CODY GAVIN-
|
|
22506949-202
| U/SLAB |
9/19/2025
|
9/19/2025
| A |
-conduit under slab
|
|
12511121-113
| P LNTL |
9/22/2025
|
9/19/2025
| C |
-
|
|
12511121-113
| P LNTL |
9/19/2025
|
9/18/2025
| C |
-
|
|
12511121-101
| FND/FT |
9/16/2025
|
9/15/2025
| A |
NEWMAN, CODY GAVIN-
|