8TH EDITION FBC (2023)
| |
| |
EARLY POWER LETTER REC'D
| |
5/28/2025 10:55:32 AM
| mwerkheiser |
FEMA FORM REQUIRED
| A-U, X-NA |
11/8/2024 10:44:35 AM
| jedwards |
HOLD 109 INSP FOR FIRE ALRM PRMT
| |
4/10/2025 10:03:53 AM
| dfeagle |
HOLD 109 INSP FOR FIRE SPRNKLR PRMT
| |
12/10/2024 2:20:19 PM
| dlyons |
HOLD 109 INSP FOR UNDERGROUND PERMIT
| |
1/7/2025 12:19:33 PM
| lnewton |
HOLD BLDG FINAL INSP FOR FIRE MARSHAL FINAL.
| |
| |
HOLD C/O FOR SITE ASBUILT APPROV
| |
| |
HOLD C/O: ORIGINAL FINISHED CONST FEMA
| |
11/8/2024 10:44:38 AM
| jedwards |
IMPACT FEE DUE
| 24-070462 |
11/25/2024 11:38:04 AM
| ewhee |
INFO NOC-
| 5937/753 |
1/3/2025 9:21:57 AM
| khart |
LANDSCAPE INSPECTION REQ
| |
| |
TERMITE BOND CO
| FL PEST / SOIL |
11/25/2024 11:51:56 AM
| mwerkheiser |
TERMITE FINAL TREATMENT PRIOR TO C/O
| |
| |
HOLD FINAL FOR SEPARATE TPO ROOF PERMIT
| |
5/7/2025 3:30:19 PM
| khart |
HOLD 105 INSP FOR FIRE PUMP
| |
9/24/2025 3:08:13 PM
| dfeagle |
HOLD 105 INSP FOR BLDG RADIO SYSTEM TEST REPORT
| |
7/11/2025 7:01:32 AM
| RDowling |