7th Edition FBC (2020)
| |
| |
|
EARLY POWER LETTER REC'D
| |
9/8/2022 9:38:26 AM
| slkling |
|
ENGINEER ELEVATION CERTIFICATION
| |
7/19/2022 8:05:12 AM
| dwintons |
|
HOLD C/O FOR SUBDIVISION ASBUILT APPROVAL
| |
4/6/2022 3:09:00 PM
| ttrezza |
|
IMPACT FEE DUE
| 22-041945 |
6/22/2022 10:15:21 AM
| dwint |
|
INFO NOC-
| 5562 / 1289 |
5/23/2022 3:35:25 PM
| clschmermund |
|
LANDSCAPE INSPECTION REQ
| |
12/15/2022 9:10:12 AM
| |
|
LOT GRADING INSP REQ PRIOR C/O
| |
12/29/2022 9:37:50 AM
| |
|
METER CAN INSPECTION
| |
9/8/2022 8:44:35 AM
| air |
|
PAID UTILITY RECEIPT REQUIRED
| SJCUD |
9/16/2022 1:35:27 PM
| slkling |
|
SOLID WASTE FEE DUE
| 22-026736 |
4/21/2022 10:59:49 AM
| kcoop |
|
TERMITE BOND CO
| TURNER;WOOD |
4/21/2022 10:59:28 AM
| kcooper |
|
TERMITE PROTECTION CERT OF COMPL
| |
7/22/2022 11:03:55 AM