7th Edition FBC (2020)
| |
| |
|
EARLY POWER LETTER REC'D
| |
8/9/2022 8:51:22 AM
| slkling |
|
ENGINEER ELEVATION CERTIFICATION
| |
6/14/2022 3:34:33 PM
| amcbroom |
|
HOLD C/O FOR SUBDIVISION ASBUILT APPROVAL
| |
3/24/2022 2:19:40 PM
| amcbroom |
|
IMPACT FEE DUE
| 22-047358 |
7/15/2022 1:04:27 PM
| dwint |
|
INFO NOC-
| 5544//625 |
4/25/2022 4:20:40 PM
| alosco |
|
LANDSCAPE INSPECTION REQ
| |
11/14/2022 10:01:08 AM
| |
|
LOT GRADING INSP REQ PRIOR C/O
| |
12/7/2022 1:58:20 PM
| |
|
METER CAN INSPECTION
| |
8/9/2022 8:51:38 AM
| air |
|
PAID UTILITY RECEIPT REQUIRED
| SJCUD |
7/29/2022 3:33:52 PM
| kturner |
|
SOLID WASTE FEE DUE
| 22-023762 |
4/8/2022 3:17:44 PM
| kcoop |
|
TERMITE BOND CO
| TURNER;WOOD |
4/8/2022 3:17:24 PM
| kcooper |
|
TERMITE PROTECTION CERT OF COMPL
| |
7/15/2022 2:15:04 PM