7th Edition FBC (2020)
| |
| |
|
EARLY POWER LETTER REC'D
| |
5/17/2022 9:20:39 AM
| slkling |
|
ENERGIZE BLDG INSPECTION
| |
5/13/2022 12:00:40 PM
| air |
|
HOLD 109 INSP FOR EXHST HD PRMT
| |
4/11/2022 1:12:07 PM
| PWebb |
|
HOLD 109 INSP FOR FIRE ALRM PRMT
| ELECTRONICALLY SUPERVISED |
3/2/2022 11:17:07 AM
| dlyons |
|
HOLD 109 INSP FOR FIRE SPRNKLR PRMT
| HVLS FANS |
2/18/2022 1:07:59 PM
| dlyons |
|
HOLD 109 INSP FOR FIRE SUP PRMT
| |
5/12/2022 10:40:04 AM
| dlyons |
|
HOLD 109 INSP FOR UNDERGROUND PERMIT
| CHECK SUPERVISED BFP |
3/23/2022 10:24:51 AM
| agedris |
|
HOLD BLDG FINAL INSP FOR FIRE MARSHAL FINAL.
| PER FM AGREEMENT. |
6/24/2022 4:01:52 PM
| |
|
HOLD C/O FOR SITE ASBUILT APPROV
| OK FOR TCO THRU 10/28/2022 PER BPP |
9/27/2022 3:57:59 PM
| bpowelson |
|
IMPACT FEE DUE
| 22-027507 |
4/25/2022 11:43:14 AM
| lbrow |
|
IMPACT FEE DUE
| 22-027507 |
4/25/2022 11:43:14 AM
| lbrow |
|
IMPACT FEE DUE
| 22-027507 |
4/25/2022 11:43:14 AM
| lbrow |
|
INFO NOC-
| 5472 / 1197 |
1/19/2022 1:33:21 PM
| clschmermund |
|
LANDSCAPE INSPECTION REQ
| |
6/22/2022 7:17:47 AM
| |
|
PAID UTILITY RECEIPT REQUIRED
| SJCUD |
7/26/2022 11:54:06 AM
| khart |
|
REINSPECTION FEE
| 22-042389 |
6/23/2022 12:01:15 PM
| Lexis |
|
REINSPECTION FEE
| 22-042389 |
6/23/2022 12:01:15 PM
| Lexis |
|
REINSPECTION FEE
| 22-042389 |
6/23/2022 12:01:15 PM
| Lexis |
|
REINSPECTION FEE
| 22-049562 |
7/26/2022 11:15:30 AM
| Lexis |
|
TERMITE BOND CO
| BELL BROTHERS TERMITE CONTROL / SOIL |
11/15/2021 9:14:00 AM
| krobshaw |
|
TERMITE PROTECTION CERT OF COMPL
| |
7/13/2022 1:42:55 PM
| slkling |
|
HOLD 109 FOR FIRE PUMP
| |
5/26/2022 1:35:26 PM
| agedris |
|
HOLD 105 FOR BDA SYSTEM TEST
| TEST RECIEVED BUILDING FAILED SYSTEM REQUIRED |
5/26/2022 1:31:15 PM
| agedris |
|
HOLD FIRE FINAL APPROVAL FOR BDA FINAL TEST REPORT
| |
9/27/2022 4:16:23 PM
| agedris |
|
HOLD 109 FOR REVISION (CO2 ALARM, PUMP ROOM RATING, EL)
| CO2 HOLD CLEARED BASED ON CONV. WITH AGEDRIS |
6/17/2022 12:57:29 PM
| agedris |