7th Edition FBC (2020)
| |
| |
|
CSTL CONST DEP PERMIT NEEDED
| |
5/25/2021 7:56:08 AM
| janoda |
|
EARLY POWER LETTER REC'D
| |
9/13/2022 11:21:37 AM
| slkling |
|
EARLY POWER LETTER REC'D
| |
9/15/2022 3:06:41 PM
| slkling |
|
EXISTING RESIDENCE TO BE REMOVED PRIOR TO C/O
| PER DEMO PERMIT 12013801 |
3/1/2023 7:26:15 AM
| ccontestabile |
|
FEMA FORM REQUIRED
| FZ -VE BFE -12' FFE- 18' (LHSM SHOULD BE ABOUT 24" BELOW FFE |
11/3/2021 1:43:30 PM
| wwoodward |
|
HOLD C/O: ORIGINAL FINISHED CONST FEMA
| VE-BFE-12' MER-14' LHSM-16.2' FFE-18.2' GAR-15' EQUIP-15' |
4/6/2023 1:01:56 PM
| ajordan |
|
IMPACT FEE DUE
| 23-001356 |
1/9/2023 6:52:46 PM
| Lexis |
|
INFO NOC-
| 5336/1191 |
8/5/2021 4:06:00 PM
| ccontestabile |
|
LANDSCAPE INSPECTION REQ
| |
4/6/2023 10:23:05 AM
| |
|
Lighting Ordinance 190 for inspection
| LIGHTING INSPECTION CONDUCTED 3/21/23 |
3/22/2023 11:03:33 AM
| tdodson |
|
LOT GRADING INSP REQ PRIOR C/O
| |
4/6/2023 9:53:42 AM
| |
|
METER CAN INSPECTION
| |
9/14/2022 1:11:42 PM
| air |
|
REINSPECTION FEE
| 23-015516 |
3/24/2023 11:45:17 AM
| Lexis |
|
REINSPECTION FEE
| 23-017821 |
4/4/2023 3:14:18 PM
| tclif |
|
SOLID WASTE FEE DUE
| ALREADY ASSESSED |
5/24/2021 4:05:06 PM
| krobshaw |
|
SWALE/CULVERT FINAL INSP REQ
| |
3/28/2023 7:16:00 AM
| air |
|
TERMITE BOND CO
| NADERS / SOIL |
5/24/2021 4:05:18 PM
| krobshaw |
|
TERMITE PROTECTION CERT OF COMPL
| |
4/5/2023 10:56:33 AM
| bshugart |
|
HOLD FL FOR SEPARATE CEDAR SHAKER/METAL ACCENT ROOF PERMIT
| SEE PERMIT 12208801 FOR ROOF PERMIT |
5/24/2022 11:18:21 AM
| ehumphreys |
|
HOLD ALL INSPECTIONS
| PILE REPORT DUE |
6/29/2022 3:01:48 PM
| janoda |