EARLY POWER LETTER REC'D
| |
4/27/2018 2:03:02 PM
| cgalloway |
|
FEMA FORM REQUIRED
| AE-9, VE-14 LHSM 18.2 NGVD 1929 |
3/31/2017 2:58:48 PM
| blaw |
|
HOLD C/O FOR SUBDIVISION ASBUILT APPROVAL
| |
12/5/2016 8:45:46 AM
| BOCC |
|
HOLD C/O: ORIGINAL FINISHED CONST FEMA
| DFE = 15' - FFE @19.2 |
5/8/2018 7:49:54 AM
| pdoty |
|
IMPACT FEE DUE Zero Out
| |
11/15/2016 3:51:17 PM
| kallen |
|
INFO NOC-
| BK 4325 PG 513 |
2/1/2017 12:35:14 PM
| bshugart |
|
LANDSCAPE INSPECTION REQ
| |
5/1/2018 4:07:48 PM
| |
|
Lighting Ordinance 190 for inspection
| PLACE DIMMER ON RECESSED CANS |
5/21/2018 9:12:31 PM
| |
|
LND SIGN OFF
| |
| |
|
LOT GRADING INSP REQ PRIOR C/O
| |
5/16/2018 9:39:33 AM
| |
|
METER CAN INSPECTION
| |
4/30/2018 3:09:18 PM
| air |
|
SOLID WASTE FEE DUE
| ALREADY ASSESSED |
1/12/2017 12:11:22 PM
| cgalloway |
|
TERMITE BOND CO
| PENNINSULAR/SOIL |
1/12/2017 12:02:05 PM
| cgalloway |
|
TERMITE PROTECTION CERT OF COMPL
| |
5/4/2018 11:54:52 AM
| cgalloway |
|
HOLD 106 ENGINEERING FOR LOWER WALL FLARE
| RELEASED AFTER ENGINEERING LETTER/CLADDING DETAIL SUBMITTED |
10/2/2017 3:03:03 PM
| ehumphreys |
|
HOLD GRADE BEAM INSPECTION FOR BEAM ELEVATION VERIFICATION
| LHSM 18.2 NGVD 1929 |
3/31/2017 2:57:46 PM
| blaw |
|
HOLD INSPECTIONS FOR PILING INSTALLATION INSPECTION REPORT
| 36' X14" TOT 37 |
3/2/2017 2:54:06 PM
| rkruse |