2004-FL BLDG CODE
| |
| |
|
EARLY POWER LETTER REC'D
| |
12/6/2006 12:00:00 AM
| KH |
|
ENERGIZE BLDG INSPECTION
| |
11/29/2006 10:45:50 AM
| RFD |
|
FEMA FORM REQUIRED
| Fema 30.9 |
7/27/2006 12:00:00 AM
| TEB |
|
HOLD BLDG FINAL INSP FOR FIRE MARSHAL FINAL.
| |
2/16/2007 3:36:16 PM
| |
|
HOLD C/O FOR SITE ASBUILT APPROV
| |
3/23/2007 12:00:00 AM
| BAF |
|
HOLD C/O: ORIGINAL FINISHED CONST FEMA
| REC'D @32.5, EQUIP @32.00; RE CASE # 93-04-195P |
2/14/2007 12:00:00 AM
| JO |
|
IMPACT FEE DUE
| 06-033575 |
10/13/2006 1:59:04 PM
| AEK |
|
INFO NOC-
| or 2643 pg 358-359 |
2/14/2006 12:00:00 AM
| CJG |
|
LANDSCAPE INSPECTION REQ
| |
2/14/2007 2:12:00 PM
| |
|
PAID UTILITY RECEIPT REQUIRED
| SEE LETTER OK FOR EARLY POWER***-* |
1/18/2007 12:00:00 AM
| TEB |
|
TERMITE BOND CO
| TURNER/SOIL |
2/6/2006 12:00:00 AM
| EJH |
|
TERMITE PROTECTION CERT OF COMPL
| |
1/18/2007 12:00:00 AM
| TEB |
|
THIS IS A THRESHOLD BUILDING
| The threshold final letter was recieved and scanned in file. |
1/31/2007 12:00:00 AM
| WJD |
|
hold on BP no insp past slab until fire sprinkler permit
| |
3/16/2006 12:00:00 AM
| PJW |
|
hold on BP no insp past slab until fire alarm permit
| |
4/11/2006 12:00:00 AM
| PJW |
|
hold on BP no insp past slab until underground permit
| |
3/16/2006 12:00:00 AM
| PJW |