DEVELOPMENT SERVICE APPROVAL REQ
| TEMP C/O TILL 8/6/01 DJH |
12/21/2001 12:00:00 AM
| DH |
|
EARLY POWER LETTER REC'D
| 04/24/01 |
| |
|
HOLD BLDG FINAL INSP FOR FIRE MARSHAL FINAL.
| OK PER R.DOWLING |
7/3/2001 12:00:00 AM
| EJ |
|
IMPACT FEE DUE
| 00-021593 $43,416.00 |
10/30/2000 12:00:00 AM
| ED |
|
INFO NOC-
| NOC OR 1509 PG 488 |
| |
|
LANDSCAPE INSPECTION REQ
| ok for co |
6/29/2001 12:00:00 AM
| JK |
|
METER CAN INSPECTION
| ENERGIZE BLDG APPRVD 05/29/01/WS |
| |
|
PAID UTILITY RECEIPT REQUIRED
| |
3/12/2001 12:00:00 AM
| KH |
|
TERMITE BOND CO
| TURNER RECVD SLAB REPORT |
| |
|
TERMITE FINAL TREATMENT PRIOR TO C/O
| RECVD TUB TRAP |
6/25/2001 12:00:00 AM
| KH |
|
HOLD FINAL FOR FIRE DAMPEN IN DRYER VENT VIA 1 HR RATED WALL
| |
4/16/2001 12:00:00 AM
| SD |
|
REC D FAULT CURRENT LTR/SINGLE PHASE 46,759 SYM AMP 120/240
| |
| |
|
HOLD INSP PAST FOUNDATION FOR STRUCT ENGINEER DOCUMENTS
| |
4/16/2001 12:00:00 AM
| SD |
|
HOLD C/O FOR DOT APPROVAL
| APPRVD SS |
4/23/2001 12:00:00 AM
| KH |