SJC Home
DescriptionInputDateWho
7th Edition FBC (2020)    
EARLY POWER LETTER   8/24/2022 3:17:30 PM khart
FEMA FORM REQUIRED X-NA 5/10/2021 12:52:44 PM wwoodward
HOLD C/O: ORIGINAL FINISHED CONST FEMA PROJECT IN X 5/10/2021 12:52:45 PM wwoodward
HOLD CO FOR PRIVATE PROVIDER CERT OF COMPLIANCE   10/31/2022 10:08:28 AM cgalloway
IMPACT FEE DUE Zero Out   3/19/2021 11:12:44 AM tsteven
IMPACT FEE REASSESSMENT NEEDED    
INFO NOC- BK 5215 PG 430 4/16/2021 11:10:21 AM krobshaw
LANDSCAPE INSPECTION REQ   10/6/2022 3:45:51 PM  
LOT GRADING INSP REQ PRIOR C/O   9/27/2022 3:47:28 PM  
METER CAN INSPECTION   8/25/2022 3:10:34 PM Priv Povider
SOLID WASTE FEE DUE ALREADY ASSESSED 4/16/2021 11:11:31 AM krobshaw
SWALE/CULVERT FINAL INSP REQ   10/27/2022 2:59:13 PM air
TERMITE BOND CO TURNER / SOIL 4/16/2021 11:10:49 AM krobshaw
TERMITE PROTECTION CERT OF COMPL   11/1/2022 4:24:15 PM ccontestabile