DescriptionInputDateWho
7th Edition FBC (2020)    
EARLY POWER LETTER REC'D   6/5/2023 10:48:50 AM khart
ENERGIZE BLDG INSPECTION   7/7/2023 4:13:53 PM air
HOLD 109 INSP FOR FIRE ALRM PRMT SUPERVISED BACKFLOW 2/7/2022 8:36:53 AM dlyons
HOLD 109 INSP FOR FIRE SPRNKLR PRMT SUPERVISED BACKFLOW 12/10/2021 8:50:57 AM dlyons
HOLD 109 INSP FOR UNDERGROUND PERMIT SUPERVISED BACKFLOW 6/23/2022 9:52:22 AM dlyons
HOLD BLDG FINAL INSP FOR FIRE MARSHAL FINAL.   8/25/2023 10:54:06 AM  
HOLD C/O FOR SITE ASBUILT APPROV OK FOR TCO THRU 9/18/2023 PER BP 9/26/2023 9:50:43 AM hsapp
IMPACT FEE DUE 23-021380 4/21/2023 10:33:49 AM lbrow
INFO NOC- BK5437 PG1602-1606 1/25/2022 2:46:10 PM khart
PAID UTILITY RECEIPT REQUIRED SJCUD 5/15/2023 11:20:16 AM kturner
REINSPECTION FEE 23-049056 8/18/2023 11:15:45 AM tclif
TERMITE BOND CO FLORIDA PEST / SOIL 10/19/2021 10:17:45 AM krobshaw
TERMITE PROTECTION CERT OF COMPL   5/15/2023 11:20:14 AM kturner
HOLD FRAMING INSPECTION 105 TRUSS PACKAGE   1/12/2023 8:59:49 AM jadams
HOLD 105 FOR PRODUCT APPROVAL   1/12/2023 8:59:47 AM jadams
HOLD 105 FOR ENERGY CALCS   1/19/2022 12:39:08 PM jadams
HOLD 109 BDA / RADIO SYSTEM TEST   3/7/2023 1:44:43 PM dfeagle
HOLD FIRE FINAL FOR BLDG RADIO SYSTEM REVISON/PERMIT   3/7/2023 1:44:44 PM dfeagle
HOLD 105 FOR MULTIPLE REVISIONS AS STATED IN REVIEW COMMENTS DO NOT COMPLETE FRAMING INSPECTION UNTIL SIGNED OFF 1/6/2022 2:01:57 PM dfeagle