7th Edition FBC (2020)
| |
| |
|
EARLY POWER LETTER REC'D
| |
3/29/2023 4:25:52 PM
| bshugart |
|
EARLY POWER LETTER REC'D
| NEED FOR NEW (4/6/23) 22302927, 22302929, 22302954 |
4/18/2023 2:14:14 PM
| bshugart |
|
ENERGIZE BLDG INSPECTION
| |
4/11/2023 7:15:29 AM
| Priv Povider |
|
FEMA FORM REQUIRED
| AE-5, X-NA |
7/15/2021 2:29:48 PM
| jadams |
|
HOLD 109 INSP FOR FIRE ALRM PRMT
| |
9/21/2022 1:40:59 PM
| dlyons |
|
HOLD 109 INSP FOR FIRE SPRNKLR PRMT
| |
6/13/2022 9:25:35 AM
| VVitori |
|
HOLD 109 INSP FOR UNDERGROUND PERMIT
| |
12/30/2021 9:53:06 AM
| SMurray |
|
HOLD BLDG FINAL INSP FOR FIRE MARSHAL FINAL.
| |
8/25/2023 3:24:04 PM
| |
|
HOLD C/O FOR SITE ASBUILT APPROV
| |
9/12/2023 4:11:21 PM
| hsapp |
|
HOLD C/O: ORIGINAL FINISHED CONST FEMA
| |
7/15/2021 2:29:53 PM
| jadams |
|
HOLD CO FOR PRIVATE PROVIDER CERT OF COMPLIANCE
| |
8/23/2023 1:52:30 PM
| kcooper |
|
IMPACT FEE DUE
| 22-042303 |
6/23/2022 9:02:08 AM
| lbrow |
|
INFO NOC-
| BK 5413 PG 1903 |
1/27/2022 3:05:37 PM
| krobshaw |
|
PAID UTILITY RECEIPT REQUIRED
| JEA |
5/22/2023 3:18:30 PM
| khart |
|
REINSPECTION FEE
| 23-050060 |
8/23/2023 8:55:46 AM
| tclif |
|
REINSPECTION FEE
| 23-051174 |
8/28/2023 12:52:44 PM
| tclif |
|
TERMITE BOND CO
| PRO TECH SERVICES / SOIL |
2/1/2022 9:01:28 AM
| bbonfanti |
|
TERMITE PROTECTION CERT OF COMPL
| |
7/28/2023 10:21:52 AM
| kcooper |
|
HOLD SLAB INSPECTION FOR POST TENISION ENGINEERING
| |
4/12/2022 10:57:38 AM
| jadams |
|
HOLD C/O FOR THRESHOLD FINAL REPORT
| |
6/2/2023 12:25:47 PM
| jadams |
|
HOLD FINAL FOR SEPARATE METAL ROOF PERMIT
| P#12307526 |
6/8/2023 1:21:22 PM
| khanson |
|
HOLD 109 FOR FIRE STAND PIPE PERMIT
| |
8/5/2022 12:21:56 PM
| VVitori |
|
HOLD 105 FOR IN BUILDING FIRE RADIO SYSTEM REVISION
| BUILDING EXEMPT PER STATUTE |
3/14/2023 1:54:36 PM
| agedris |
|
HOLD 105 FRAMING FOR MEETING TO ADDRESS FIRE COMMENT 9&13
| |
5/11/2023 12:28:19 PM
| agedris |