7th Edition FBC (2020)    
EARLY POWER LETTER REC'D 22311121 /22311122 /22311123 /22311124 7/30/2025 10:56:02 AM clschmermund
ENERGIZE BLDG INSPECTION   8/4/2025 8:14:19 AM air
FEMA FORM REQUIRED AE-12, X-NA 6/3/2026 1:42:18 PM jbrown
HOLD 109 INSP FOR EXHST HD PRMT   6/24/2025 7:42:44 AM lnewton
HOLD 109 INSP FOR FIRE ALRM PRMT PREACTION 12/4/2025 12:20:59 PM lnewton
HOLD 109 INSP FOR FIRE SPRNKLR PRMT QUICK RESPONSE 1/15/2025 3:52:55 PM lnewton
HOLD 109 INSP FOR FIRE SUP PRMT   6/16/2025 9:12:20 AM lnewton
HOLD 109 INSP FOR UNDERGROUND PERMIT   7/30/2024 2:24:34 PM lnewton
HOLD BLDG FINAL INSP FOR FIRE MARSHAL FINAL.    
HOLD C/O FOR SITE ASBUILT APPROV    
HOLD C/O: ORIGINAL FINISHED CONST FEMA *FINISHED CONSTRUCTION FEMA CERTIFICATE REQUIRED*  
IMPACT FEE DUE 25-044759 8/14/2025 8:13:40 AM nbrad
INFO NOC- 5886/1889 1/17/2024 10:22:28 AM jcrodriguez
INFO NOC- BK6012 PG185 9/13/2024 2:23:55 PM mmount
LANDSCAPE INSPECTION REQ    
PAID UTILITY RECEIPT REQUIRED JEA 2/11/2026 3:19:40 PM krobshaw
REINSPECTION FEE 62500322 602 4/17/2026 $55 4/20/2026 2:44:59 PM lnewton
TERMITE BOND CO MCCALL SERVICE/SOIL 12/8/2023 10:54:03 AM khart
TERMITE PROTECTION CERT OF COMPL    
SEPARATE PERMIT NEED FOR TPO/METAL ROOF   5/7/2025 3:43:22 PM khart
HOLD C/O FOR FINAL THRESHOLD REPORT   6/4/2026 2:32:13 PM jedwards
HOLD 109 FOR FIRE PUMP INSTALLED UNDER CEP BUILDING PERMIT 10/15/2025 3:55:46 PM PWebb
HOLD 109 FOR DAMPER INSPECTIONS    
HOLD 105 FOR RADIO ENHANCEMENT SYSTEM TEST BDA SUBMITTED AND APPROVED 10/15/2025 3:57:50 PM PWebb
HOLD 109 FOR SMOKE CONTROL SYSTEM PERMIT   4/8/2026 6:09:20 AM PWebb
NO FINAL APPROVAL FOR MED GAS 3RD PARTY INSPECTION REPORT   6/24/2026 7:53:51 AM RDowling
NO SPRINKLER FINAL CONDUCTED UNTIL CEP PUMP APPROVAL AND CO. COMMENT 52  
HOLD 109 FOR REVISION FOR STAIR SIGNAGE (COMMENT 7) REVISION SUBMITTED 6/30/2026 9:21:32 AM PWebb
HOLD 109 FOR CLEAN AGENT SYSTEM (NOVEC 1230) COMMENT 11- COMPLETED 12/17/25 6/30/2026 3:20:36 PM jlhatcher
HOLD 109 FOR SPECIAL LOCKS REVISION    
HOLD 109 FOR REVISION FOR LABORATORY CHEMICALS (NFPA 45) REVISION SUBMITTED. 6/30/2026 8:09:34 AM PWebb
HOLD 109 FOR NFPA 801 ENGINEERS ANALYSIS/REPORT COMMENT 17 7/22/2026 7:03:03 AM RDowling
HOLD FINAL INSPECTION FOR 3RD PARTY NFPA 801 INSPECTION COMMENT 17 7/22/2026 7:03:04 AM RDowling
HOLD 109 FOR MECHANICAL REVISION TO CLARIFY WALLS COMMENT 18- APPROVED AND SIGNED OFF BY FIRE MARSHAL DOWLING 10/15/2025 4:13:26 PM PWebb
HOLD 109 FOR ELECTRICAL REVISION FOR COMMENT 43 APPROVED AND SIGNED OFF BY FIRE MARSHAL DOWLING. 10/15/2025 4:15:49 PM PWebb