SJC Home
DescriptionInputDateWho
7th Edition FBC (2020)    
EARLY POWER LETTER REC'D   9/7/2022 1:51:54 PM slkling
ENERGIZE BLDG INSPECTION   9/16/2022 12:57:06 PM air
HOLD 109 INSP FOR FIRE ALRM PRMT   11/10/2021 9:38:34 AM dlyons
HOLD 109 INSP FOR FIRE SPRNKLR PRMT   6/2/2022 2:23:34 PM lnewton
HOLD BLDG FINAL INSP FOR FIRE MARSHAL FINAL.   11/17/2022 2:36:03 PM  
HOLD C/O FOR SITE ASBUILT APPROV OK FOR TCO THRU 1/8/23 PER BP 12/21/2022 3:46:36 PM bpowelson
IMPACT FEE DUE 22-035440 5/25/2022 3:10:04 PM dwint
INFO NOC- 5421 / 1130 11/17/2021 9:53:27 AM clschmermund
LANDSCAPE INSPECTION REQ LANDSCAPE TO BE INSPECTED W/ASBULT 22-103 11/16/2022 3:14:40 PM  
PAID UTILITY RECEIPT REQUIRED SJCU 11/16/2022 10:43:21 AM ecannon
TERMITE BOND CO PRO-TEK / SOIL 10/6/2021 10:29:35 AM krobshaw
TERMITE PROTECTION CERT OF COMPL   10/14/2022 10:30:49 AM cgalloway