EARLY POWER LETTER REC'D   3/29/2022 2:14:25 PM cgalloway
ENERGIZE BLDG INSPECTION   3/28/2022 11:10:48 AM air
HOLD 109 INSP FOR EXHST HD PRMT   10/21/2021 10:32:31 AM dlyons
HOLD 109 INSP FOR FIRE ALRM PRMT   7/28/2021 10:49:20 AM PWebb
HOLD 109 INSP FOR FIRE SPRNKLR PRMT   1/13/2022 7:34:48 AM PWebb
HOLD 109 INSP FOR FIRE SUP PRMT   2/18/2022 4:14:11 PM dlyons
HOLD 109 INSP FOR UNDERGROUND PERMIT   1/13/2022 7:34:51 AM PWebb
HOLD BLDG FINAL INSP FOR FIRE MARSHAL FINAL.   7/19/2022 2:06:26 PM  
HOLD C/O FOR SITE ASBUILT APPROV   7/21/2022 10:07:38 AM smorrison
IMPACT FEE DUE 22-021024 3/31/2022 7:50:38 AM nbrad
INFO NOC- 5241/891 6/9/2021 1:13:38 PM edegrande
LANDSCAPE INSPECTION REQ   6/3/2022 7:33:06 AM  
PAID UTILITY RECEIPT REQUIRED JEA 5/11/2022 7:41:48 AM slkling
REINSPECTION FEE 62100365 606 5/12/2022 $55 6/10/2022 9:13:12 AM khart
REINSPECTION FEE 62100292 601 5/12/2022 $55 6/10/2022 9:13:16 AM khart
TERMITE BOND CO TURNER; SOIL 2/3/2021 11:28:12 AM bshugart
TERMITE PROTECTION CERT OF COMPL   5/24/2022 9:56:21 AM slkling
HOLD 102 SLAB INSP. TRUSS PACKAGE   6/15/2021 10:29:34 AM jadams
HOLD 109 FIRE/SMOKE DAMPER INSPECTION   2/25/2022 8:18:49 AM agedris
HOLD 109 FOR GENERATOR PERMIT ON MAIN ELECTRICAL PERMIT 22104730 2/11/2022 10:47:20 AM edegrande
HOLD 109 FOR EMERGENCY LIGHT REVISION SPECS PROVIDED FOR INVERTER SYSTEM. ADDRESS REVISION 10/12 10/12/2021 1:00:14 PM PWebb
HOLD 105 FOR IN BUILDING RADIO ENHANCEMENT SYSTEM TEST REPORT RECIEVED BUILDING PASSED 3/23/2022 10:13:45 AM agedris